Package - 3

Sr. No Nature of Work Status
1 Barricading

Fabricated till date - 1708 (94% of the Project scope is completed)

Placed at site -1600

  • Mumbai Central- In progress
  • Mahalaxmi- In progress
  • Science Museum- In progress
  • Acharya Attre Chowk- In Progress
  • Worli- In Progress
2 Rehabilitation &; Resettlement  -
3 Traffic Diversion 

Traffic Diversion plans have been prepared and Contractor has taken the necessary approval from Traffic Police.

4 Geo-technical investigation

100 % Completed

5 Tree Cutting/transplantation

Mumbai Central, Mahalaxmi, Science Museum, Acharya Attrey Chowk and Worli : Tree Authority Committee Permission Received

Tree Cutting and transplantation is in progress -

Mumbai Central- 42 / 43 cut and 45 / 56 transplanted

Mahalaxmi- 28 / 33 cut and 110 / 122 transplanted

Science Museum- 56 / 107 cut and 34 / 87 transplanted

Acharya Attre Chowk- 76 / 76 cut and 27 / 31 transplanted

Worli- 71 / 78 cut and 125 / 134 transplanted

6 Building condition Survey In Progress.