Package - 3

Sr. No Nature of Work Status
1 Barricading

Fabricated till date - 1708 (94% of the Project scope is completed)

Placed at site -1600

  • Mumbai Central- In progress
  • Mahalaxmi- In progress
  • Science Museum- In progress
  • Acharya Attre Chowk- In Progress
  • Worli- In Progress
2 Rehabilitation &; Resettlement  _______
3 Traffic Diversion 

Traffic Diversion plans have been prepared and Contractor has taken the necessary approval from Traffic Police.

4 Geo-technical investigation

100 % Completed

5 Tree Cutting/transplantation

Mumbai Central, Mahalaxmi, Science Museum, Acharya Attrey Chowk and Worli : Tree Authority Committee Permission Received

Tree Cutting and transplantation is in progress -

Mumbai Central- 42 / 43 cut and 46 / 56 transplanted

Mahalaxmi- 32 / 33 cut and 111 / 122 transplanted

Science Museum- 56 / 108 cut and 37 / 87 transplanted

Acharya Attre Chowk- 74 / 76 cut and 26 / 31 transplanted

Worli- 77 / 78 cut and 124 / 134 transplanted

6 Building condition Survey In Progress.
7 Tunneling Progress

TBM has been arrived at Science Museum.

Tunneling not yet started.

Site Acceptance Test for Slurry separation plant of TBM has been done.

8 Segment Production Progress

21 %  of the total scope has been completed. 

9 Secant Piling Progress

Station Box Area:

Mumbai Central - 81 % completed

Mahalaxmi – 86% completed

Science Museum – 96% completed

Acharya Attre Chowk – 78% completed

Worli – 87 % completed

10 Excavation

Science Museum Launching Shaft:

33,550/60,000 cu.m has been completed.

11 Base Slab Progress

_______