Package - 5

Sr. No Nature of Work Status
1 Barricading

Vidyanagari Station - This Week - 0 ,Total progress - 382 ,Scope - 446

BKC Station - This Week - 0 ,Total progress - 357 ,Scope - 767

Santacruz Station - This Week - 0 ,Total progress - 517 ,Scope - 600 

Dharavi Station - This Week - 0 ,Total progress - 235 ,Scope - 339

Casting Yard - This Week - 0 ,Total progress - 153 ,Scope - 432

2 Rehabilitation & Resettlement 

__________

3 Traffic Diversion 

BKC Station – 220 m completed out of 220 m.

Vidyanagri Station – 70 m completed out of 710 m.

4 Geo-technical investigation

Vidyanagari Station - Completed

BKC Station - Remaining Boreholes in Mangroves Area

Santacruz Station - Completed

Dharavi Station - Completed

 

5 Tree Cutting/transplantation

Tree Cutting Work has been completed at Dharavi, Santacruz stations and cutting in BKC and Vidyanagri is in progress

3 Trees cut at Vidyanagari Station in last week.

4Trees have been transplanted from Vidyanagari Station.

6 Building condition Survey

__________

 

Upload File: 
Date: 
Saturday, December 2, 2017 - 15:00
Package Type: 
Top