Package - 5

Sr. No Nature of Work Status
1 Barricading

Vidyanagari Station - This Week - 0 ,Total progress - 382 ,Scope - 446

BKC Station - This Week - 0 ,Total progress - 357 ,Scope - 767

Santacruz Station - This Week - 0 ,Total progress - 517 ,Scope - 600 

Dharavi Station - This Week - 0 ,Total progress - 235 ,Scope - 339

Casting Yard - This Week - 0 ,Total progress - 153 ,Scope - 432

2 Rehabilitation & Resettlement 

__________

3 Traffic Diversion 

BKC Station – 220 m completed out of 220 m.

Vidyanagri Station – 70 m completed out of 710 m.

4 Geo-technical investigation

Vidyanagari Station - Completed

BKC Station - Completed

Santacruz Station - Completed

Dharavi Station - Completed

 

5 Tree Cutting/transplantation

Tree Cutting & Transplantation

Dharavi

Tree Cutting - Scope - 5, Total Progress - 5, Remarks - Completed

Tree Transplant - Scope - 43, Total Progress - 25, Remarks - Ongoing

BKC

Tree Cutting - Scope - 67, Total Progress - 53, Remarks - Ongoing

Tree Transplant - Scope - 40, Total Progress - 22, Remarks - Ongoing

Vidyanagari

Tree Cutting - Scope - 47, Total Progress - 42, Remarks - Ongoing

Tree Transplant - Scope - 69, Total Progress - 54, Remarks - Ongoing

Santacruz

Tree Cutting - Scope - 7, Total Progress - 7, Remarks - Completed

Tree Transplant - Scope - 23, Total Progress - 21, Remarks - Ongoing

 

6 Building condition Survey

__________

 

Upload File: 
Date: 
Saturday, February 17, 2018 - 15:00
Package Type: 