Package - 6

Sr. No Nature of Work Status
1 Barricading

SAHAR Road Metro station

All construction Works is going on within
secured barricading area .

CSIA T1 Metro station

Completed

CSIA T2 Metro station

Completed

Construction Depot JVLR (GI Sheets)

Completed

 

2 Rehabilitation & Resettlement  ______
3 Traffic Diversion 

SAHAR ROAD STATION : Road diversion: Stage-1 Completed

Subway work in progress

Sahar Shadow Road: Work in Progress

Caping beam & Flood Wall: Work in progress.

CSIA INTERNATIONAL STATION (SC 2) : Internal Road: Work in progress.
 

4 Geo-technical investigation

SAHAR Road Metro station

Completed

Sahar Road to International Station

BHT-26,27 near hutment
area ,Not posiible.

CSIA T1 Metro Station

Completed

CSIA T2 Metro Station

Completed

5 Tree Cutting/transplantation

CSIA T1 -  Total progress - 3 , Scope - 3 ,  Completed

Transplantation - 59 out of 112

Sahar Rorad - Total progress - 4 , Scope - 4 , Completed

Transplantation - 177 out of 226

CSIA T2 - Total progress - 0 , Scope - 0 , Completed

Transplantation -  4 out of 4 completed

6 Building condition Survey

Pre-condition survey this week - 1

Total Progress - 60

Scope - 60

7 Tunneling Progress

_______

8 Segment Production Progress

Permanent Rings: Total progress - 1388, Scope - 5050

9 Secant Piling Progress

CSIA T1 Metro station

Secant piles: Total progress - 808, Scope - 808

Micro piles: Total progress - 156, Scope - 156

Sahar road Station

Secant piles: Total progress - 1015, Scope - 1121

Subway secant piles: Total progress - 67, Scope - 67

CSIA T2 Metro Station

Secant piles: Total progress - 1298, Scope - 1298

10 Excavation

CSIA T1 Metro station

Station box: Total progress - 123725 Cum. Scope - 290288 Cum.

Sahar road Station

Launching shaft: Total progress - 42000 Cum. Scope - 42000 Cum.

Station box: Total progress - 88767 Cum. Scope - 223229 Cum.

Retrieval Shaft: Total progress - 18208 Cum. Scope - 64664 Cum.

CSIA T2 Metro Station

Launching Shaft: Total progress - 68140 Cum. Scope - 68140 Cum.

Retrival Shaft: Total progress - 66915 Cum. Scope - 71112 Cum.

Station Box: Total progress - 132721 Cum. Scope - 356478 Cum.

11 Base Slab Progress

_______

Upload File: 
Date: 
Monday, June 18, 2018 - 15:00
Package Type: 
Top