Package - 6

Sr. No Nature of Work Status
1 Barricading

SAHAR Road Metro station

68% Completed

CSIA T1 Metro station

Handed over land portion Completed

CSIA T2 Metro station

Completed

Construction Depot JVLR (GI Sheets)

Completed

 

2 Rehabilitation & Resettlement  ______
3 Traffic Diversion 

SAHAR ROAD STATION : Road diversion: Stage-1 Completed

4 Geo-technical investigation

SAHAR Road Metro station

Completed

Sahar Road to International Station

BHT-26,27 near hutment
area ,Not posiible.

CSIA T1 Metro Station

Completed

CSIA T2 Metro Station

Completed

5 Tree Cutting/transplantation

CSIA T1 -  Total progress - 3 , Scope - 3 ,  Completed

Transplantation - 49 out of 112

Sahar Rorad - Total progress - 4 , Scope - 4 , Completed

Transplantation - 145 out of 226

CSIA T2 - Total progress - 0 , Scope - 0 , Completed

Transplantation -  4 out of 4 completed

6 Building condition Survey

Pre-condition survey this week - 1

Total Progress - 60

Scope - 60