Package - 3

Sr. No Nature of Work Status
1 Tunneling & Segment Production Progress

Science Museum-Worli ( Tanasa-1) - 775/1381 rings has been erected

2nd TBM Science Museum-Worli ( Tanasa-2) - 589/1370  rings has been erected.

Segment Production Progress:

50 %  of the total scope of permanent rings has been completed.

2 Excavation

Mumbai Central Station:
1,05,131 / 2,14,855 cu.m has been completed.

Mahalaxmi Station:
77,498  / 1,61,729 cu.m has been completed.

Science Museum Station:
1,85,340  / 2,15,000 cu.m has been completed.

Acharya Attre Chowk Station:
32,464  / 1,87,969 cu.m has been completed.

Worli:

1,07,391 / 1,62,056 cu.m has been completed.

3 Base Slab Progress 

Mumbai Central:

7.2 % of the total scope has been completed.

Science museum:

44.08 % of the total scope has been completed.

Worli:

7.9 % of the total scope has been completed.

Concourse Slab Progress:

Science museum: 12.6 % of the total scope has been completed.

4 Secant Piling Progress 

Station Box Area:

Mumbai Central - 100 % completed

Mahalaxmi – 100 % completed

Science Museum – 100 % completed

Acharya Attre Chowk – 99.6 % completed

Worli – 100 % completed

5 Rehabilitation &; Resettlement

Completed

6 Building condition Survey In Progress.
7 Tree Cutting/transplantation

Tree Cutting and transplantation is in progress -

Mumbai Central- 42 / 43 cut and 46 / 56 transplanted

Mahalaxmi- 33 / 33 cut and 117 / 122 transplanted

Science Museum- 56 / 108 cut and 37 / 87 transplanted

Acharya Attre Chowk- 74 / 76 cut and 26 / 31 transplanted

Worli- 77 / 78 cut and 124 / 134 transplanted

8 Traffic Diversion

Completed

9 Geo-technical investigation

100 % Completed

10 Barricading

100 % completed. In progress with the construction works.

Upload File: 
Date: 
Sunday, August 18, 2019 - 09:45