Media Centre

    • Utility Investigation - Worli
    • Barricade repainting - Worli
    • Temporary road diversion preparatory works - Science Museum
    • Secant piling - Mumbai Central
    • Secant piling - Worli
    • Secant piling - Science Museum
    • Secant piling - Acharya Attre Chowk
    • Secant piling - Mahalaxmi
    • Guide wall construction Worli
    • Utility Trenching - Mumbai Central
    • Secant Piling - Mumbai Central
    • SWD connection - Science Museum
    • Secant Piling - Mahalaxmi
    • Barricade cleaning Worli
    • Guide wall construction - Worli
    • Segment stacking - Casting Yard
    • Secant piling - Worli
    • Capping beam works - Science Museum
    • SWD connection work - Science Museum
    • Trial ring assembly - Casting Yard
    • Guide wall for secant Piling - Acharya Attre
    • Pile chipping for capping beam casting - Science Museum
    • Secant Piling - Worli
    • Secant Piling - Mumbai Central
    • Secant Piling - Mahalaxmi
    • Secant Piling - Science Museum
    • Segment Casting - Casting Yard
    • Barricade cleaning - Acharya Attre
    • Secant Piling - Worli
    • Segment reinforcement work - Casting Yard
    • Guide wall shuttering - Acharya Attre
    • Segment Casting - Casting Yard
    • Secant Piling - Mumbai Central
    • Utility trenching - Mahalaxmi
    • Secant Piling - Mahalaxmi
    • SWD connection works - Science Museum
    • Barricade board cleaning Casting Yard
    • TBM slurry treatment plant foundation work - Science Museum
    • Segment reinforcement work Casting Yard
    • Segment Casting - Casting Yard
    • Temporay road diversion work Science Museum
    • Rebar cage fabrication Worli
    • Secant Piling Worli
    • Secant Piling Acharya Attre
    • Secant Piling Mumbai Central
    • Secant Piling Mahalaxmi
    • Barricade board cleaning Acharya Attre
    • Barricade board cleaning Mahalaxmi
    • Electric cable diversion Worli
    • Utility Shifting Acharya Attre
    • Utility Investigation Worli
    • Utility Investigation Mumbai Central
    • TBM slurry treatment plant setup - Science Museum
    • Secant Piling Science Museum
    • Secant Piling Mahalaxmi
    • Secant Piling Acharya Attre
    • Segment reinforcement work - Casting Yard
    • Segment Casting - Casting Yard
    • PCC for guide wall in progress Acharya Attre Chowk
    • Gas line diversion work Mahalaxmi
    • Secant Piling Mumbai Central
    • Batching plant setup - Construction Depot
    • Utility Investigation - Mahalaxmi
    • Utility diversion - Acharya Attre
    • Segment trial ring assembly work Casting Yard
    • Segment Reinforcement work - Casting Yard
    • Labour colony setup - Casting Yard
    • Segment stacking Casting Yard
    • Secant piling - Worli
    • Secant piling - Science Museum
    • Secant piling - Mumbai Central
    • Secant piling - Acharya Attre
    • Road widening - Acharya Attre
    • Aerial view Science Museum
    • Labour colony establishment - Casting Yard
    • Gantry crane commissioning - Casting Yard
    • Utility trenching - Worli
    • Utility trenching - Acharya Attre Chowk
    • Utility trenching - Mumbai Central
    • Utility trenching - Mahalaxmi
    • SWD diversion - Science Museum
    • MESS construction
    • Secant piling - Science Museum
    • Secant piling - Mahalaxmi
    • Secant piling - Worli
    • Segment stacking - Casting Yard
    • Aerial view Mumbai Central site
    • Tree transplantation on joint event MMRC & Western Railway - Mumbai Central
    • Street pole removal Worli
    89
    Package - 3
    11/12/2017
    • Permanent rings for tunnel
    • Works at Churchgate Station
    • Works at Hutatma Chowk Station
    • Works at Vidhan Bhavan Station
    • Works at Cuffe Parade Station
    • Diversion of Major Utility
    • Assembling crane for Churchgate Station
    • Depot area at MIDC land Colaba
    • Piling works at Churchgate Station
    • Works near heritage building at DN Road for Hutatma Chowk Station
    • Decking works near launch shaft at Cuffe Parade
    • Training to crane operators on safe lifting methods by third party.
    • Supporting existing utilities
    • Commencement of strut erection at Launch Shaft.
    • Cage lowering for hand piles
    • Vibration monitoring at heritage buildings
    • Utility Diversion at Vidhan Bhavan Station
    • Works at Vidhan Bhavan Station
    • Precast rings and structural steel fabrication
    • Piling works at Churchgate
    • New piling rig arrived at Churchgate station
    • Piling works at Hutatma Chowk station
    • Preparations to commence piling at on-road portion at Vidhan Bhavan station
    • Activities at launch shaft at Cuffe Parade station
    • Piling works at Churchgate Station at Jamshedjee Tata Road
    • Launch Shaft portion at Cuffe Parade
    • Vidhan Bhavan station Aerial view
    • Hutatma Chowk station Aerial view
    • Aerial view of works at Churchgate Station
    • All machines operated only after safety checks
    • Cage making at pre-cast yard
    • Additional rig commissioning at Cuffe Parade Station
    • Managing traffic movement at DN Road
    • Mock Fire Emergency drill near Cuffe Parade
    • Trial run of fire tender in the location of Traffic Diversion
    • Preparation to commence Launch Shaft Excavation at Cuffe Parade
    • Trial run of traffic diversion near Vidhan Bhavan Station
    • Installation of special barriers to restrict noise
    • Prevented flooding in Work areas and nearby areas
    • Boier erection at casting yard for facilitating steam curing
    • Piling Rig No. 4 unloaded for Hutatma Chowk Station
    • Traffic signages in English & Marathi
    • Tilt meter in a Heritage Building
    • Traffic notice in English & Marathi
    • Securing pedestrians walkway
    • Works at Launch Shaft side at Cuffe Parade Station
    • Works at DN Road for Hutatma Chowk Station (towards CST)
    • Works at DN road for Hutatma Chowk Station ( South Side)
    • View of works at Cuffe Parade (South Side)
    • View of works at Vidhan Bhavan Station
    • Works at Launch Shaft (Piling and Utility Diversions)
    • View of Jamshedji Tata road for construction of Churchgate Station
    • Installation of noise barrier to reduce inconvenience to residents
    • Implementation of Traffic Diversion at Jamshedji Tata road
    • Pathway for pedestrians at Jamshedji Tata road
    • Commencement of piling at Churchgate Station
    • Calibration of Batching Plant (60 Cu.m/hr)
    • Third party inspection of Piling Rigs
    • Soldier Pile for trench preparation for pipe jacking
    • Providing safe and clean access to pedestrians
    • Progress review at Vidhan Bhavan Station
    • MMRC MD visits Station Cuffe Parade
    • MMRC MD 's visit at Hutatma Station
    • Project review by MMRC MD
    64
    Package - 1
    10/12/2017
    • TBM Nayanagar
    • TBM Nayanagar
    • Aerial view of Nayanagar Site
    • Dadar
    • Dadar Construction Site
    • Aerial view of Siddhivinayak construction site.
    • Aerial view of Siddhivinayak construction site.
    • Segment Casting
    • Casting Yard
    • Shitladevi
    • Shitladevi
    • Siddhivinayak  piling
    • Siddhivinayak  piling
    • Casting Yard
    • Casting Yard
    • Nayanagar Shaft
    • Casting Yard
    • Dadarf road Diversion
    • Shitladevi road diversion
    • Nayanagar Shaft
    • Casting Yard Segments
    • Traffic Diversion Dadar
    • Guide wall casting at Dadar
    • Nayanagar Shaft Excavation
    • Nayanagar Shaft Excavation
    • Segment stacking
    • Traffic Diversion Dadar
    • Utility Diversion Dadar
    • Ring assembly testing
    • Nayanagar Excavation
    • Nayanagar Excavation
    • Nayanagar Excavation
    • Casting Yard segment casting
    • Casting Yard stacking bay
    • Bus queue shelter shifting
    • Shitladevi transplantation
    • Aarey transplantation
    • Nayanagar
    • Siddhivinayak
    • Siddhivinayak
    • Dadar traffic diversion
    • Dadar tree cutting
    • Dadar Utility Diversion
    • Shitladevi road works
    • Casting Yard - Segment casting
    • Dadar road works
    • Dadar & Shitladevi road works
    • Nayanagar micro pile gantry foundation
    • Nayanagar shaft excavation
    • Nayanagar shaft excavation
    • Capping beam Nayanagar
    • Casting Yard moulds
    • Casting Yard
    • Dadar house keeping
    • Nayanagar Micropile
    • Dadar road widening
    • Ravindra Natya Mandir
    • Casting Yard Gantry Foundation
    • Casting Yard segment
    • Dadar road
    • Siddhivinayak piling
    • Siddhivinayak piling
    • Dadar road widening
    • Casting Yard cage preparation
    • Shitladevi Road Excavation
    • Siddhivinayak
    • Siddhivinayak cage building
    • Shitladevi Road Widening
    • Siddhivinayak piling
    • Capping Beam at Nayanagar
    • Road Wideniing works at Dadar
    • Road Widening works at Dadar & Shitladevi
    • Segment Casting Yard
    • Segment Yard
    • Casting Yard
    • Nayanagar
    • Siddhivinayak
    • Sapling Distribution - Project Neighbourhood
    • Tree distribution in Project Neighbourhood
    • Tree Neighbourhood program
    • Project Neighbourhood
    • Tree Plantation
    • Casting Yard Batching Plant setup
    • Casting Yard 1st Segment Demoulding
    • Casting Yard 1st Segment Demoulding
    • Nayanagar Piling Works
    • Nayanagar
    • Casting Yard National Safety Week
    • Casting Yard National Safety Day
    • Safety Week Casting Yard
    • Casting Yard  Binding
    91
    Package - 4
    04/12/2017
    • SWD Pipe laying(Santacruz)
    • Caping beam(BKC)
    • Secant Piling at Station Box
    • Capping Beam (Dharavi)
    • Piling (BKC)
    • Launching Shaft (Vidyanagari)
    • Gabion Wall(Dharavi)
    • Excavation of Launching Shaft Ongoing at Vidyanagari Station
    • Labour Camp Erection ongoing at Vidyanagari Station
    • Piling Work ongoing at Santacruz Station
    • Piling Work ongoing at Dharavi Station
    • Mangrooves Area Cleaning on going at BKC Station
    • BKC - Piling, Backfilling
    • BKC Project Office - Flooring Works
    • Santacruz-Micro Piling
    • Vidyanagri - Road for Traffic Diversion
    • Vidyanagri North Shaft - Excavation 1
    • Vidyanagri North Shaft - Excavation 2
    • Santacruz-Secant Piling
    • Dharavi - Secant Piling
    • Dharavi - Reinforcement fixing for Capping Beam
    • Excavation work ongoing at Vidyanagari Station
    • Piling work ongoing at Dharavi Station
    • Piling Work ongoing at Santacruz Station
    • BKC - North Launching Shaft
    • BKC Steel Yard - Batching Plant Erection Ongoing
    • BKC - Project Office
    • Vidyanagri - Piling (Gr 1 to 6 - West)
    • Dharavi - Pile Chipping for Capping Beam (Gr 1 to 6 - Nallah Side)
    • Dharavi - 2nd Piling Rig Mobilised
    • Vidya Nagari North Shaft - Pile Chipping for Capping Beam Preparation
    • Dharavi - Piling Activity at Gr 10-17 (Nallah Side)
    • Vidya Nagari - Piling Activity in North Shaft
    • Project office progress
    • Vidya Nagari - RCC work ongoing for Road Diversion
    • Tree cutting - Santacruz
    • Vidya Nagari North Shaft - Pile Chipping for Capping Beam Preparation
    • BKC - Capping Beam at North Launching Shaft
    • Dharavi - Piling at Grid 1-6 (West)
    • Vidyanagri - 1200 mm Water Line - Shutdown Preparation
    • Vidyanagri - Cable Anchor Insertion
    • BKC - Trial Run Traffic Diversion
    • Dharavi - Pile Concreting
    • Dharavi - Pile Concreting
    • Vidyanagri - 1200mm dia Water Line Encasing
    • Vidyanagri - Capping Beam
    • Vidyanagri - GSB for Road Diversion
    • Piling work ongoing at BKC Station
    • Piling work on going at Dharavi Station
    • Rig machine for GI shifted to Mid Ventillation Shaft
    • Welding and cutting work on going at Vidyanagari Station.
    • Cable Anchoring - Vidyanagri North Shaft
    • Piling - BKC North Shaft
    • Piling - Dharavi (Gr 1 to 6)
    • Project Office - BKC
    • Meter Room Brick Work on Going at BKC Station
    • Exacavation for Drain on going at Dharavi Station
    • Tench Work on going at Vidyanagari Station
    • Trench Excavation ongoing at Santacruz Station
    • Boring on going for TBH 19 at Santacruz Station
    • Boring on going for TBH 19 at Santacruz Station
    • RCC work at BKC Station for project office.
    • Utility Shifting work on going at Vidyanagari Station
    • Trial Pit Excavation at Santacruz Station
    • Foundation Footing Progress for Project Site office BKC Station
    65
    Package - 5
    02/12/2017
    • CST - Safety Training on Gas Cutting
    • CST - Safety Training on Gas Cutting
    • CST - Fixing of Reinforcement Cage for Reaction frame
    • Grant Road - King Post Welding
    • Casting Yard - Vacuum Lifting for Segment
    • Casting Yard - Vacuum Lifting for Segment
    • Casting Yard - Concreting for Segment
    • Casting Yard - Concreting for Segment
    • Grant Road - Lying of new sewer line
    • Girgaon - Mobilization of RIG
    • Girgaon - Polymer Tank Setup
    • WTC - Welding for Strut for Preload
    • WTC - bracing in Strut
    • CST - Mucking by Muck basket
    • Grant Road - Utility Diversion at Phase 1
    • Girgaon - Excavation for Utility Diversion in progress at Phase 1
    • CST - Launching Shaft
    • Grant Road - Arial View of Phase 3
    • Grant Road - Arial View of Phase 1
    • Girgaon - Barricading in Phase 3
    • CST - Mucking by Muck basket
    • CST - Cleaning of Muck between Pile
    • CST - Foundation for Chiller Tower
    • CST - Launching Shaft
    • CST - Muck Bin Side wall
    • Casting Yard - Cylinder Stacking
    • Casting Yard - Segment Reinforcement Welding
    • Casting Yard - Reinforcement Fixed in Segment
    • Casting Yard - Segment Reinforcement Welding
    • Casting Yard - Segment Reinforcement Welding
    • Casting Yard - Segment Reinforcement Welding
    • TBM - FAT - T58
    • Casting Yard - Segment Stacking
    • TBM - FAT
    • Casting yard - Preparatory work for Segment casting
    • Casting Yard - Lowering of Cage
    • Casting Yard - Micro-Finishing
    • Grant Road - Traffic Diversion
    • Grant Road - Traffic Diversion
    • Grant Road - Traffic Diversion
    • CST - Launching Shaft Area
    • CST - Load cell fixing between struts
    • CST - packing Concrete for waler
    • Grant Road - Trail Run for traffic diversion
    • Grant Road - Trail Run for traffic diversion
    • Grant Road - Trail Run for traffic diversion
    • Grant Road - Secant Pile Cage lowering
    • Grant Road - Utility Supporting wall
    • Grant Road - Utility Supporting wall
    • CST - Leveling for Crane Pad foundation
    • Grant Road -  MMRC's MD visit to Grant Road Site
    • CST - MMRC's MD visit to CST site Launching Shaft
    • Wadala - Segment Curing by Gunny Bags
    • Wadala - Aggregate Bin
    • CST - Muck Bin
    • CST - 1st Level Strut
    • CST - 1st Level Strut
    • CST - Preparatory work for Tree Transplantation
    • CST - Preparatory work for Tree Transplantation
    • CST - Transportation of Tree for Transplantation
    • Wadala - Master Ring Assembly
    • Wadala - Master Ring Assembly
    • CST - Waler beam for Rock Anchoring
    • CST - Gantry Crane Foundation
    • CST - Survey level checking for Anchoring
    • Grant Road - Piling Rig Calibration
    • CST - Inserting of Anchoring cable
    • CST - RCC breaking for Gantry Foundation
    • Wadala - Erection of Gantry Crane
    • CST - Level checking for tower crane foundation
    • CST - Muck Bin Excavation
    71
    Package - 2
    24/11/2017
    • Ms. Ashwini Bhide, MD, MMRC along with team MMRC witnessing the first excavation of Mumbai Metro Line - 3
    • Ms. Ashwini Bhide, MD, MMRC along with team MMRC witnessing the first excavation of Mumbai Metro Line - 3
    • Ms. Ashwini Bhide, MD, MMRC along with team MMRC witnessing the first excavation of Mumbai Metro Line - 3
    • Ms. Ashwini Bhide, MD, MMRC along with team MMRC witnessing the first excavation of Mumbai Metro Line - 3
    4
    Commencement of tunneling at Nayanagar
    10/11/2017
    • Drain Work at Sahar Shadow road
    • Excavation at Sahar Road Station
    • Piling at SaharRoad Station
    • Sahar Shadow road
    • Retrieval Shaft Excavation at CSIA International Station
    • Excavation at CSIA International Station
    • Excavation at Sahar Road Station
    • Micropiling at CSIA Domestic Station
    • Launching Shaft Excavation at CSIA International Station
    • Excavation at Sahar Road Station
    • Capping beam construction at CSIA International Station
    • Retieval Shaft at CSIA International Station
    • Excavation at Sahar Road Station
    • Excavation at Sahar Road Station
    • Excavation at Sahar Road Station
    • Launching Shaft at CSIA International Station
    • Piling at CSIA International Station
    • Capping Beam at CSIA International Station
    • Segment cage making at Casting yard
    • Labour colony at Construction Depot - Copy
    • Labour colony at Construction Depot - Copy
    • Car parking raft demolishen work at CSIA Domestic Station
    • 900 mm dia drain diversion at CSIA Domestic Station
    • Excavation at Sahar Road Station
    • Shadow Road work at Shar Road Station
    • Excavation at Sahar Road Station
    • Excavation at Sahar Road Station
    • Flood protection wall construction at CSIA Domestic Station
    • 900 mm Storm water drain diversion at CSIA Domestic Station
    • Housekeeping at CSIA Domestic Station
    • Capping beam at  CSIA International Station
    • Launching shaft excavation at CSIA International Station
    • Flood wall & Road work at CSIA International Station
    • Excavation at Sahar Road Station
    • Excavation at Sahar Road Station
    • Excavation at Sahar Road Station
    • Retrieval Shaft at CSIA International Station
    • Barricade Cleaning at CSIA Domestic Station
    • Capping Beam at CSIA International Station
    • Site Office work at CSIA International Station
    • Road work at CSIA International Station
    • Capping beam at Shahar Road Station
    • Road work at CSIA International Station
    • Road Diversion at Sahar Road Station
    • Launching Shaft at Sahar Road Station
    • Launching Shaft at Sahar Road Station
    • 1800 mm Dia. water line diversion at CSIA Domestic Station
    • Shadow Road at Sahar Road Station
    • Pile breaking for capping beam at CSIA International Station
    • Piling work at CSIA International Station
    • Piling at CSIA Domestic Station
    • Launching shaft+ Station Box Exvcavation at Sahar Road Station
    • Capping Beam at CSIA Domestic Station
    • Pile cage making at CSIA Domestic Station
    • Flood Protection wall at CSIA International Station
    • Flood Protection wall construction at Sahar Road Station
    • Capping Beam at CSIA Domestic Station
    • Capping Beam at CSIA Domestic Station
    • Launching Shaft at Sahar Road Station-min
    59
    Package - 6
    06/11/2017
    • Shiv Sena Chief, Shri. Uddhav Thackeray, visited Azad Maidan site office to review Colaba-Bandra-SEEPZ Metro-3 corridor.
    • Ms. Ashwini Bhide, MD, MMRC, made a detailed presentation to Shri. Uddhav Thackeray.
    • Shri. Uddhav Thackeray also visited the shaft at Azad Maidan.
    3
    Shiv Sena Chief - Visits Azad Maidan Site.
    11/10/2017
    • Piling work in progress at MIDC Station
    • Gantry rail fixing work in progress at MIDC Station
    • Excavation work in progress at MIDC Station
    • Mid Shaft.
    • Mid Shaft.
    • Marol Naka Station.
    • Marol Naka Station.
    • Marol Naka Station
    • Piling work in progress at MIDC station
    • MIDC excavation work
    • Piling & Capping beam work in progress at MIDC Station
    • MIDC station police quarters work area
    • Arial view of mid shaft (Pali Ground)
    • Precast segment curing at Casting Yard
    • Precast segment curing at Casting Yard
    • Segment mould at mould stock yard in Casting Yard
    • Utility shifting work in progress at MIDC Station
    • Line Drilling work is in progress at Mid Shaft
    • 45T Gantry crane erection work at Mid Shaft
    • Sedimentation tank rebar fixing work in Casting Yard
    • 45T Gantry crane erection work at Mid Shaft
    • Muck pit foundation work in in progress at Mid Shaft
    • Excavation work in progress at MIDC Station
    • Fabrication work in progress at Marol Naka Station
    • Capping beam work in progress at MIDC Station
    • Pile No. P297 boring is in progress by 2nd rig in SEEPZ Station
    • Muck pit excavation work is in progress at ramp (Launching Shaft area)
    • MIDC ESIC Area
    • Kingpost work in progress at MIDC Station
    • 3rd pour of 2nd ring beam rebar fixing completed at Mid Shaft
    • Line drilling is in progress at Mid Shaft
    • Casting work is in progress at 2nd pour of 2nd ring beam
    • Segment mould checking work beforle casting at Casting Yard
    • Rebar cage fabrication work at SEEPZ Station
    • Pile No. S324 boring work is in progress at SEEPZ Station
    • 45T gantry erection is in progress at Mid Shaft
    • Levelling work is in progress at ramp
    • Levelling work is in progress at ramp
    • Cage lowering work for pile no. S324 at SEEPZ Station
    • Trial trench work is in progress at ERTL building in Seepz station
    • Line drilling work is in progress at Mid Shaft
    • Muck disposal is in progress by crawler crane at Mid Shaft
    • Second ring beam 1st floor casting completed at Mid Shaft
    • Second ring beam rebar fixing work is in progress at Mid Shaft
    • Utility identification & shifting in progress at MIDC station
    • Utility identification & shifting in progress at MIDC station
    • Backfilling work is in progress at Ramp Area
    • Disel shed fabrication work is in progress at Casting Yard
    • Earth dressing & levelling work is in progress at ramp area
    • Ground improvement work is in progress at Casting Yard
    • JIG fabrication work is in progress at Casting Yard
    • PCC work is in progress for ground improvement at ramp area
    • Segment ring assemble work is in progress at Casting Yard
    • Segment stock yard ground PCC work is in progress at Casting Yard
    • Soil excavation and rock drilling work is in progress at Mid Shaft
    • Secant pile boring ins in progress at SEEPZ Station
    56
    Package - 7
    01/10/2017
Top