Photo Gallery

    • Fifth TBM breakthrough for Mumbai Metro 3 corridor at Chhatrapati Shivaji Maharaj International Airport- T2 metro station.
    • Starting it's course under Metro Line 1 at MarolNaka The 92 mtr long TBM Wainganga-3 tunneled at an average of 4.2 mtrs daily through the rocky strata made of Basalt, volcanic Breccia shaping the tunnel with 937 RCC cement rings.
    • Starting it's course under Metro Line 1 at MarolNaka The 92 mtr long TBM Wainganga-3 tunneled at an average of 4.2 mtrs daily through the rocky strata made of Basalt, volcanic Breccia shaping the tunnel with 937 RCC cement rings.
    3
    Fifth TBM breakthrough for Mumbai Metro 3 corridor.
    13/02/2019
    • Domestic airport station
    • International Airport Station
    • International Airport Station
    • Retrival shaft work at Sahar
    • Retrival shaft work at Sahar
    • Sahar road metro station work
    • T1 station excavation work
    • Utility hanging work at Sahar road station
    • T2 station box
    • Station wall shuttering work at Sahar road station
    • Excavation work at Domestic Airport Station
    • Erection of tower crane at Domestic Airport Station
    • Tower crane completion at Sahar Road Station
    • Base Slab(G15.35-16.85) reinforcement at International Airport Station
    • Excavation at Sahar Road Station
    • Waler beam work at Domestic airport station
    • Excavation at Domestic airport station
    • Reinforcement of base slab at Domestic airport station
    • Excavation at International airport station
    • 1800 mm Dia. water line Diversion at CSIA Domestic Station
    • 900 mm Storm water drain at CSIA Domestic Station
    • Casting Yard
    • Gantry
    • Excavation at Domestic Airport Station
    • Excavation at Retrieval Shaft Sahar Road Station
    • Excavation at Retrieval Shaft at Domestic Airport Station
    • Excavation below Utility Support System at Sahar Road Station
    • Earthmat Grid (15-18) at Sahar Road Station
    • Excavation at International Airport Station
    • Initial Drive Finished Tunnel SC2-SSR Downline at International Airport Station
    • Excavation at Retrieval Shaft Sahar Road Station
    • Tunnel-Ring Installation at International Airport Station
    • Excavation at International Airport Station
    • Excavation at Domestic Airport Station
    • Excavation at Domestic Airport Station
    • Excavation below Utility Support System at Sahar Road Station
    • Excavation at Sahar Road Station
    • Suspender Erection at Utility Support System at Sahar Road Station
    • Excavation at International Airport Station
    • Base Slab Grid 11-13 at International Airport Station
    • Tunnel-Ring Installation at International Airport Station
    • TBM Retrieval Programme at International Airport Station
    • TBM Retrieval at International Airport Station
    • Tunnel ring installation at International Airport Station
    • Base Slab grid 10-13 work in progress at International Airport Station
    • Base Slab grid 18-20 at Sahar Road Station
    • Walkway at Sahar Road Station
    • Secant pile work in progress for NATM at Domestic Airport station
    • Excavation at Domestic Airport station
    • Excavation at Domestic Airport station
    • Excavation at International Airport Station
    • MMRCL MD visit at Package - 6 site
    • Inaugration of initial drive at International Airport Station
    • Initial drive started between International Airport Station to Sahar Road Station
    • Shadow road inauguration at Sahar Road Station
    • Shadow road commisioned on 27.07.18
    • Capping Beam at CSIA Domestic Station Box
    • TBM Parts at CSIA International station
    • Domestic NATM Secant pile
    • Domestic North retreival shaft excavation
    • Sahar station box excavation work
    • International retrieval shaft exacavation work
    • Sahar Utility hanging work
    • CSIA International station Excavation work
    • Subway work at Sahar road station
    • CSIA International shaft Launching shaft work
    • Excavation near Launching shaft
    • Excavation at International retrieval shaft
    • Launching shaft base slab at Launching shaft
    • Excavation at Sahar Retrieval shaft
    70
    Package - 6 (CSA(domestic)-CSA(international)-Sahar )
    10/02/2019
    • Aerial view - Acharya Attre
    • Excavation - Science Museum
    • Aerial view - Mumbai Central
    • Excavation - Worli
    • Tansa - 1
    • Base slab casting - Science Museum
    • Base slab casting - Science Museum
    • Excavation - Mahalaxmi
    • Excavation - Mumbai Central
    • Excavation - Worli
    • Excavation - Worli
    • Mahalaxmi
    • Acharya Attre
    • Mumbai Central
    • Worli
    • Tansa - 1 (1)
    • Tansa - 2 (2)
    • Casting Yard
    • Mumbai Central
    • Science Museum
    • Acharya Attre
    • Acharya Attre
    • Mahalaxmi
    • Casting Yard
    • Acharya Attre
    • Acharya Attre
    • Mumbai Central
    • Mumbai Central
    • Science Museum
    • Mahalaxmi
    • Worli
    • Science Museum
    • Acharya Attre
    • Mahalaxmi
    • Mahalaxmi
    • Mahalaxmi
    • Mumbai Central
    • Science Museum
    • Science Museum
    • Science Museum
    • Worli
    • Science Museum
    • Science Museum
    • Mumbai Central
    • Mumbai Central
    • Mahalaxmi
    • Mahalaxmi
    • Mahalaxmi
    • Acharya Attre
    • Acharya Attre
    • Acharya Attre
    • Acharya Attre
    • Aerial view - Mahalaxmi
    • Aerial view - Worli
    • Aerial view - Science Museum
    • Reinforcement fixing for traffic deck - Worli
    • Steel decking installation - Mumbai Central
    • 900 MM SWD diversion - Worli
    • Tanasa - 1 Initial Drive
    • Tunnel eye casting - Science Museum
    • Utility support installation - Acharya Attre
    • Excavation - Science Museum
    • Aerial view - Acharya Attre
    • MAHANAGAR Gas line diversion - Mahalaxmi
    • Temporary ring erection - TBM
    • Steel deck installation - Mumbai Central
    • Aerial view - Mumbai Central
    • Excavation - Science Museum
    68
    Package - 3 ( Mumbai Central-Mahalaxmi-Science Museum-...
    10/02/2019
    • Station Chatrapati Shivaji - Wall and column works
    • Grant Road Station - Sewerline & Decking works
    • Grant Road Station - Sewerline & Decking works
    • Grant Road Station - Sewerline & Decking works
    • Grant Road Station - Capping BEam Breaking
    • Grant Road Station - Sewer and Decking Works
    • Grant Road Station - Sewer Line Excavation works
    • Grant Road Station - Sewerline wokrks
    • Tunnel Rail Maintenance
    • Station Chatrapati Shivaji - Base Slab Pour-05 Reinforcement Works
    • Station Chatrapati Shivaji - Column works
    • Station Chatrapati Shivaji - Wall Construction
    • Grant Road Station - Sewerline Diversion
    • Station Chatrapati Shivaji Pour04 base slab concreting
    • Girgaon Station - building demolition
    • Grant Road Station - Sewerline diversion works
    • Grant Road Station - Sewerline diversion works
    • Grant Road Station - Sewerline diversion works
    • CST - Station Concourse
    • CST - Station base slab front
    • CST - Station Excavation
    • Girgaon - Building Demolition
    • Girgaon Station Demolition wroks
    • Grant Road Station - Sewerline diversion works
    • Grant Road Station - Sewerline diversion works
    • Grant Road Station - Excavation and Strutting
    • SCS - Pour - 04
    • Girgaon Building Demolition
    • SCS - Rebar binding or tying work for main wall Down line side
    • SCS - GC 7 column shuttering working in progress
    • Grant Road Station  - Phase 3 excavation works
    • SCS-Excavation for diversion of 600mm and 450mm water main is in progress with 4 labours opposite to Cama Hospital EE2
    •  Grant Road Station- Excavation at Phase 03 for decking
    • Grant Road Station- Barricade maintenance
    • CST- 3rd pour completed for station
    •  Base Slab Pour 3 - CST Station
    •  Capping Beam Grant Road Station
    •  Excavation Work Near Pannalal Terrace for Decking
    • Batching plant
    • Capping beam - Grant Road Station
    • Road Breaking - Grant Road Station
    • Road Rectification
    • Secant Pile - Grant Road Station
    • Soldier Pile - Grant Road Station
    • Traffic Diversion - Girgaon Station
    • Base Slab 3rd pour - PCC - CST
    • Pedestrain Walkway - Grant Road Station
    • Rock Breaking - CST
    • Secant Pile - Grant Road Station
    • Traffic Diversion - GRant Road Station
    50
    Package - 2 ( CST-Kalbadevi-Girgaon-Grant Road )
    10/02/2019
    • Curing of Concourse Slab at Vidhan Bhavan
    • First Concourse Slab Concrete Pour in UGC01 at Vidhan Bhavan
    • Muck Removal by Gantry
    • NATM Tunnels under construction at Cuffe Parade
    • Safety Month Valedictory Function
    • Safety Month Valedictory Function
    • Concourse Slab Rebar Progress in Vidhan Bhavan Station
    • Excavation Progress in Grid 2-7 at Churchgate Station
    • Excavation Progress near LS at Cuffe Parade Station
    • NATM shaft Permanent Works Progress at Cuffe Parade Station
    • Concourse Staging at Vidhan Bhavan Station
    • Excavation Progress in South SB at Hutatma Chowk Station
    • Excavation Progress near Petroleum House at Churchgate Station
    • Permanent Works Progress in NATM at Cuffe Parade Station
    • Base to Concourse Walls and Columns Progress in Vidhan Bhavan Station
    • Excavation Progress in Grid 2-9 at Churchgate Station
    • Excavation Progress near LS at Cuffe Parade station
    • Flag Hoisting - Safety Month Inauguration
    • Safety Month Inauguration Function
    • Permanent Base Slab Progress in Grid 10-12 at Vidhan Bhavan Station
    • Excavation Progress in SB near LS at Cuffe Parade Station
    • Excavation Progress near Petroleum House at Churchgate Station
    • Wall and Column Progress at Vidhan Bhavan Station
    • Permanent Base Slab Progress at Vidhan Bhavan Station
    • Utility Supporting and Excavation Progress near cross deck at Churchgate Station
    • Base Slab Progress in grid 8-10 at Vidhan Bhavan Station
    • Excavation Progress at Churchgate Station near Petroleum House
    • NATM Shaft Progress at Cuffe Parade Station
    • Wall Progress and Excavation Progress at Vidhan Bhavan Station
    • Base Slab Rebar Progress and Wall Progress in grid 6-8 at Vidhan Bhavan Station
    • Excavation Progress near Hotel Samrat at Churchgate Station
    • Excavation Progress near Petroleum House at Churchgate Station
    • Excavation Progress in Grid 3-9 at Hutatma Chowk Station
    • Strut Erection and Excavation Progress in Grid 19-24 at Hutatma Chowk Station
    • Base Slab and Rebar Progress at Vidhan Bhavan Station
    • Boom Placer Concreting at Cuffe Parade Station
    • Excavation Progress at Cuffe Parade Station
    • Excavation Progress in Grid 3-9 at Hutatma Chowk Station
    • Bird Eye view - Cuffe Parade Station
    • Bird Eye view - Churchgate Station
    • Excavation progress near Citibank at Hutatma Chowk Station
    • Permanent base slab progress at Vidhan Bhavan Station
    • Base Slab PCC at Cuffe Parade Station
    • Base Slab Casting at Vidhan Bhavan Station
    • Excavation in progress - Churchgate Station
    45
    Package - 1 ( Cuffe Parade-Vidhan Bhavan-Churchgate )
    10/02/2019
    • MIDC
    • Marol Naka
    • MIDC
    • Marol Naka
    • MIDC
    • SEEPZ
    • SEEPZ TBM lowering
    • SEEPZ
    • Marol Naka
    • MIDC
    • SEEPZ
    • Marol Naka
    • MIDC
    • Tunnel - 1
    • Tunnel - 2
    • Ramp Site
    • Marol Naka
    • MIDC
    • MIDC
    • SEEPZ
    • Marol Naka
    • Marol Naka
    • MIDC
    • SEEPZ
    • MIDC
    • Marol Naka
    • Marol Naka
    • MIDC
    • Marol Naka
    • MIDC
    • Ramp Shaft
    • SEEPZ
    • Marol Naka
    • Marol Naka
    • SEEPZ
    • MIDC
    • MIDC
    • Marol Naka
    • MIDC
    • SEEPZ
    • SEEPZ
    • Marol Naka box - A
    • Marol Naka box - B
    • MIDC
    • SEEPZ
    • Marol Naka Box - A
    • Marol Naka
    • Marol Naka
    • Marol Naka
    • Marol Naka
    • SEEPZ
    • MIDC
    • MIDC
    • Marol Naka
    • MIDC
    • MIDC
    • Casting Yard
    • Marol Naka
    • Marol Naka
    • MIDC
    • Mid Shaft
    • Ramp
    • Seepz
    • MIDC
    • MIDC
    • MIDC
    • MIDC
    • MIDC
    • Ramp
    • SEEPZ
    • TBM Assembling
    • SEEPZ
    • Tunneling in progress - Wainganga
    74
    Package - 7 ( Marol Naka-MIDC-SEEPZ )
    10/02/2019
    • Tunneling by New Austrian Tunneling Method (NATM ) commenced.
    • Tunneling commenced at the south end of BKC Station for the 153m long tunnel below Mithi River.
    • Tunneling commenced at the south end of BKC Station for the 153m long tunnel below Mithi River.
    • This will facilitate stabling of spare train during operations and also act as a Sick Siding.
    4
    Tunneling by New Austrian Tunneling Method (NATM )...
    06/02/2019
    • MMRC successfully conducts its first twin tunnel breakthrough at Dadar Metro station. TBM Krishna 1 and 2 have tunneled from Nayanagar to Dadar.
    • First Twin Tunnel Breakthrough of Mumbai Metro Line - 3 Project
    • A Herrenknecht make TBMs Krishna 1 & 2 equipped with Earth Pressure Balance Tech tunneled their way through the rocky strata made of Basalt, Breccia & tuff for 506 & 479 days.
    • With this feat MMRC achieves 35% of total work completion which includes 18Kms of tunneling.
    4
    First Twin Tunnel Breakthrough of Mumbai Metro Line - 3...
    31/01/2019
    • Bandra Station Diversion
    • BKC
    • Bandra Station Excavation
    • Santaceuz Station Excavation
    • Santaceuz Station Excavation
    • Dharavi Station Excavation
    • Vidyanagari Station Excavation below strut
    • BKC ITO Junction Piling
    • BKC Excavation (19-35)
    • Dharavi Phase-2 Decking
    • Santacruz west wall
    • Santacruz east wall
    • Vidyanagari excavation Gr-04-06
    • Vidyanagari Excavations
    • BKC Station Excavations
    • Santacruz Station Excavations
    • Dharavi Station Cable Diversion
    • Dharavi Station Anchoring Gr (15-17)
    • BKC Station Excavation
    • Vidyanagari Base Slab Work
    • Vidyanagari Excavation
    • BKC Station
    • BKC Station South Shaft
    • Santacruz Excavation
    • Bandra Station Excavation Gr - 01 - 14
    • Bandra Station Excavation Gr - 19 - 35
    • Santacruz Gantry Erection
    • Vidya Nagri Station Excavation Station Box
    • Vidya Nagri Station Shotcrete South Shaft
    • Dharavi Station Cable Diversion
    • Bandra Station Excavation
    • Santacruz Station - Excavation
    • Santacruz Station - Micro Piling
    • Vidyanagari Station - Excavation
    • Vidyanagari Station TBM Muck pit
    • Bandra Station ITO junction piling
    • Bandra Station North Shaft base slab
    • Dharavi Station - Canti lever slab casting
    • Dharavi Station - Kingpost east wall
    • Santacruz Station - Consolidated grouting
    • Bandra Station-Traffic diversion (G19-25)
    • Dharavi Station-King post
    • Bandra Station-South shaft
    • Dharavi Station-Secant piling(Ancillary)
    • Vidyanagari Station 600mm Pipe line
    • Bandra Station Road construction - Junction
    • Dharavi Station Road construction North junction
    • Dharavi Station Road construction South junction
    • Vidyanagari Station Struts
    • Santacruz Station Traffic Diversion (South End)
    • PCC Casting
    • 600mm Pipeline Diversion - East wall
    • East wall -1200mm Pipeline
    • Flood wall construction - West wall
    • PCC Casting - Launching shaft
    • T61 - Mucking
    • Bandra Station north shaft
    • Dharavi station gabion wall
    • Dharavi station piling east wall
    • New Police Station - Santacruz Station
    • North Shaft
    • North Shaft - Vidyanagari Station
    • TBM lowering has commenced at Vidyanagri North Launching shaft
    • TBM lowering has commenced at Vidyanagri North Launching shaft
    • TBM lowering has commenced at Vidyanagri North Launching shaft
    • SWD Pipe laying(Santacruz)
    • Caping beam(BKC)
    • Secant Piling at Station Box
    • Capping Beam (Dharavi)
    • Piling (BKC)
    • Launching Shaft (Vidyanagari)
    • Gabion Wall(Dharavi)
    • Excavation of Launching Shaft Ongoing at Vidyanagari Station
    • Labour Camp Erection ongoing at Vidyanagari Station
    • Piling Work ongoing at Santacruz Station
    • Piling Work ongoing at Dharavi Station
    76
    Package - 5 ( Dharavi-BKC-Vidyanagari-Santacruz )
    20/01/2019
Top