Project Status

The MML-3 Project is divided into 18 main packages of ‘Project’ & ‘System’ wings.

Package wise status of the project is as under:

Packages Nature of Work Name of Contractor Amt Status Target for Contract Award
Package 1 Civil Works – Tunnels & Stations L&T-STEC JV Rs. 2,988.53 cr Letter of Acceptance Issued to Contractor Awarded
Package 2 Civil Works – Tunnels & Stations HCC-MMS JV Rs. 2,521.89 cr Letter of Acceptance Issued to Contractor Awarded
Package 3 Civil Works – Tunnels & Stations M/S DOGUS-SOMA Rs. 2,557.84 cr Letter of Acceptance Issued to Contractor Awarded
Package 4 Civil Works – Tunnels & Stations M/S CEC-ITD CEM-TPL JV Rs. 2,830.10 cr Letter of Acceptance Issued to Contractor Awarded
Package 5 Civil Works – Tunnels & Stations M/S J. Kumar-CRTG Rs. 2,817.02 cr Letter of Acceptance Issued to Contractor Awarded
Package 6 Civil Works – Tunnels & Stations M/S J.Kumar-CRTG Rs. 2,118.40 cr Letter of Acceptance Issued to Contractor Awarded
Package 7 Civil Works – Tunnels & Stations L&T-STEC JV Rs. 2,281.45 cr Letter of Acceptance Issued to Contractor Awarded
Package 8 Civil – Depot SAM (INDIA) BUILTWELL PVT LTD Rs. 328.26 cr Letter of Acceptance Issued to Contractor Awarded
Package 9 Plant & Equipment for Depot - - Tender documents under preparation. -
Package 10 Track Works - - PQ bids are under finalization. Nov, 2017
Package 11A Traction Works

CONSORTIUM OF ALSTOM TRANSPORT INDIA LTD & ALSTOM TRANSPORT S.A.

Rs. 272.43 cr

Contract Agreement signed with bidder on 28.03.18.

Awarded
Package 11B Power Supply Works

M/s LARSEN & TOURBO LIMITED 

Rs. 338.37 cr

Contract Agreement signed with bidder on 06.04.18

Awarded
Package 12 Signaling & Train control, PSD, Telecommunication System and M&E SCADA - -

NOC for Financial Bid Evaluation Results received from JICA on 16.10.2018

Oct, 2018
Package 13 Station Security System - - - -
Package 14 Automatic Fare Collection - -

Technical Bids opened on 18.05. 2018.

Technical Bid Evaluation is under progress

Nov, 2018
Package 15 Tunnel Ventilation & Environmental Control System - -

Bids opened on 11.09.2018 for Phase-1.

Bid Evaluation under progress.

-
Package 16A Escalator Works - -

Bids opened on 20.02.18.

Technical Bid Evaluation completed for Lot 1 & 2.

Financial Bids of Lot -2 opened on 26.06.2018 and Evaluation under progress.

-
Package 16B Elavator/Lift Works - -

Bids opened on 30.01.18.

Technical Bid Evaluation completed for Lot 1 & 2.

Financial Bids of Lot -2 opened on 01.06.2018 and Evaluation under progress.

-
Package 17 Rolling Stock CONSORTIUM OF ALSTOM TRANSPORT INDIA LTD & ALSTOM TRANSPORT S.A. -

Contract agreement signed with bidder on 10th September 2018

Awarded
Package 18 General Consultant - - General Consultants engaged. May, 2016