Weekly progress report for package-2

Updated as on: 09th Feb 2020

 Sr. NoNature of WorkStatus
1Tunneling & Segment Production Progress

TBM - 1 Tunneling completed (TBM dismantalling in progress)

Temporary ring: Scope - 12 Completed

CST - SKD: Scope - 476 Completed

SKD - SGG: Scope - 499  Completed

SGG - SGR: Scope - 1,110 Completed

SGR - SMC: Scope - 635 Completed

TBM - 2

Temporary ring: Scope - 12 Completed

CST - SKD: Scope - 482 Completed

SKD - SGG: Scope - 488  Completed

SGG - SGR: Scope - 1,123 Completed

SGR - SMC: Total progress - 422, Scope - 639

Note:

TBM 2 stopped due to Parsi Fire Temple Issue on 20.07.2018 and resumed on 30.11.18

Second time stopped on 6.12.18 & resumed on 10.12.18

The productivity of TBM 2 is low due to unanticipated ground condition

Segment Production

Permanent Rings (including Upline & Downline)

SCS - SKD: Scope - 961 Completed

SKD - SGG: Scope - 713 Completed

SGG - SGR: Scope - 1,913 Completed

SGR - SMC: Scope - 991 Completed

Temporary Rings (including Upline & Downline)

SCS: Scope - 20 Completed

SKD: Scope - 277 Completed

SGG: Scope - 313 Completed

SGR: Scope - 287 Completed

2Excavation 

CST Station

Launching shaft: Scope - 25,859 Cum. Completed

Station Box (with extended concourse) - Scope - 1,26,691 Cum. Completed

Entry and Exit- Total Progress - 11,310 Cum. Scope - 29,956  Cum.

Grant Road

Station Box- Total Progress - 59,938 Cum. Scope - 1,03,536 Cum.

EE-1(Phase-02) - Total Progress - 8,829, Scope - 9,329

EE-2(Phase-05) - Total Progress - 2,364, Scope - 2,959

EE-3 (Phase-08) - Scope - 2,686

Girgaon

EE-2 (Swami Niwas) - Scope - 2,010

Station Box EE-3 (Extended conc.) -  Total Progress - 24,036, Scope - 1,39,980

Kalbadevi

Station Box- Total Progress

K-1 Box - Total Progress - 2,307, Scope - 26,621

K-2 Box -  Total Progress - 11,798, Scope - 52,000

3Base Slab Progress

CST

Station Box: Total Progress - 180, Scope - 250 

4Secant Piling Progress 

CST Station

Primary pile - Station Box: Scope - 359 Completed

Secondary pile Station Box: Scope - 352 Completed

Primary pile - Entry & Exit: Total progress - 620, Scope - 662

Secondary pile - Entry & Exit: Total progress - 628, Scope - 661

Grant Road Station

Primary pile: Total progress - 370, Scope - 371

Secondary pile: Scope - 373 Completed

Primary pile - Entry & Exit: Total progress - 53, Scope - 56

Secondary pile - Entry & Exit: Total progress - 48, Scope - 56

Girgaon Station

Primary pile Station Box: Scope - 353 Completed

Secondary pile Station Box: Total progress - 340, Scope - 345

Primary pile - Entry & Exit: Scope - 88 Completed

Secondary pile - Entry & Exit: Scope - 88 Completed

Kalbadevi Station K-2 Box

Primary Pile Station Box: Scope - 167 Completed

Secondary Pile Station Box: Scope - 167 Completed

Kalbadevi Station K-1 Box

Primary Pile Station Box: Scope - 96 Completed

Secondary Pile Station Box: Scope - 96 Completed

5Rehabilitation & Resettlement 

Rehabilitation & Resettlement is in progress.

Compensation meeting in progress with project affected residents in Kalbadevi and Girgaon.

6Building condition Survey

Pre - Condition Survey

Total Progress - 884

Scope - 1,004

Note: Additional 25M Topography survey on either of ZOI completed

7Tree Cutting/transplantation

CST - Total Progress - 47 , Scope - 91

CST - Transplantation - Total Progress - 62 , Scope - 97

Grant Road  - Total Progress - 28 , Scope - 28

Grant Road Transplantation - Total Progress - 21 , Scope - 21

Girgaon - Total Progress - 10 , Scope - 11

Girgaon Transplantation - Total Progress - 9 , Scope - 9

New Plantation at Aarey Colony  - Total Progress - 205 , Scope - 35

8 Traffic Diversion 

Permission for Traffic Diversion at Girgaon station received and  trial run road diversion started from 18th May 2017.

Trail run for traffic diversion at Grant road done on 20th July’2017 and road diversion started from 27th July’2017.

9Geo-technical investigation

Geo-technical investigation for Stations as well as Tunnel completed.

10Barricading

Barricading for CST Station Box, Wadala Casting Yard and WTC completed.

Barricading in Grant Road completed for Garden Side.

Structural Steel barricading for Median done at Grant Road.

Barricading in Girgaon completed for 619 RM out of 619 RM (Approx.)

Barricading in Kalbadevi station started as per land available on 29.09.18