Weekly progress report for package-3

Updated as on: 20th Sep 2020

Sr. NoNature of WorkStatus
1Tunneling & Segment Production Progress

Science Museum-Worli ( Tanasa-1) - 1382/1382 rings has been erected Completed

2nd TBM Science Museum-Worli ( Tanasa-2) - 1372/1372  rings has been erected.

Segment Production Progress:

79.78 %  of the total scope of permanent rings has been completed.

2Excavation

Mumbai Central Station:
2,14,144 / 2,14,855 cu.m (99.65%) has been completed.

Mahalaxmi Station:
1,51,939  / 1,61,729 cu.m (93.95%) has been completed.

Science Museum Station:
2,12,786  / 2,17,540 cu.m (94.23%) has been completed.

Acharya Attre Chowk Station:
97,984  / 1,87,969 cu.m (50.87%) has been completed.

Worli:

1,62,056 / 1,62,056 cu.m ( 100%) has been completed.

3Base Slab Progress 

Mumbai Central:

68.58 % of the total scope has been completed.

Science museum:

84.80 % of the total scope has been completed.

Worli:

87.58 % of the total scope has been completed.

Mahalaxmi:

43.61 % of the total scope has been completed.

Concourse Slab Progress:

Mumbai Central:

33.59 % of the total scope has been completed

Science museum:

63.75 % of the total scope has been completed.

Worli:

11.09 % of the total scope has been completed.

Roof Slab Progress:

Mumbai Central:

13.28 % of the total scope has been completed

Science museum:

31.23% of the total scope has been completed.

4Secant Piling Progress 

Station Box Area:

Mumbai Central - 100 % completed

Mahalaxmi – 100 % completed

Science Museum – 100 % completed

Acharya Attre Chowk – 100 % completed

Worli – 100 % completed

5Rehabilitation &; Resettlement

Completed

6Building condition SurveyIn Progress.
7Tree Cutting/transplantation

Tree Cutting and transplantation is in progress -

Mumbai Central- 42 / 43 cut and 46 / 56 transplanted

Mahalaxmi- 33 / 33 cut and 117 / 122 transplanted

Science Museum- 56 / 108 cut and 37 / 87 transplanted

Acharya Attre Chowk- 74 / 76 cut and 26 / 31 transplanted

Worli- 77 / 78 cut and 124 / 134 transplanted

8Traffic Diversion

Completed

9Geo-technical investigation

100 % Completed

10Barricading

100 % completed. In progress with the construction works.