Weekly progress report for package-5

Updated as on: 13th Sep 2020

 Sr. NoNature of WorkStatus
1Tunneling & Segment Production Progress

TBM Drive - VDN to SC-Godavari 01(T61)-Upline

 Permanent Rings: Scope - 2074 Completed

Sacrificial Rings - Scope - 9 Completed

TBM Drive - VDN to SC-Godavari 02(T60)-Downline

Permanent Rings: Scope - 2050, Total progress - 2050 Completed

Sacrificial Rings - Scope - 9 Completed

TBM Drive – BKC to VDN(S63)-Down Line

Permanent Rings: Scope - 634 Completed

Sacrificial Rings - Scope - 8 Completed

TBM Drive – BKC to VDN(S64)-Up Line

Permanent Rings: Scope - 635 Completed

Sacrificial Rings - Scope - 8 Completed

TBM Drive – BKC to SDH(S63)-Down Line

Permanent Rings: Scope - 1074, Total progress - 1074 Completed

Sacrificial Rings - Scope - 8 Completed

TBM Drive – BKC to SDH(S63)-UpLine

Permanent Rings: Scope - 1060, Total progress - 1060 Completed

Sacrificial Rings - Scope - 8 Completed

Segment Production Progress:

Mahulgaon Casting Yard

Permenant Rings - Scope - 5262, Total Progress - 2276

Sacrificial Rings - Scope - 435, Total Progress - 169

2Excavation 

Station box(BKC): Scope - 377624, Total progress - 3,65,227

Station Box(Santacruz): Scope - 106000, Total progress - 1,04,500

Station Box(Vidyanagri): Scope - 118062, Total progress - 1,53,838

Station Box(Dharavi): Scope - 179000, Total Progress - 1,76,250

3Base Slab Progress 

Permanent Works: BKC

Base Slab: Scope - 474 M, Total Progress - 315 M

Concourse Slab: Scope - 474 M, Total Progress - 204 M

Roof Slab: Scope - 474 M, Total progress - 192 M

Platform Slab: Scope - 674 M, Total progress - 41 M

Permanent Works: Vidyanagri

Base Slab: Scope - 250 M, Total Progress - 208 M

Concourse Slab: Scope - 250 M, Total Progress - 191 M

Roof Slab: Scope - 250 M, Total progress - 139 M

Platform Slab: Scope - 250 M, Total progress - 68 M

Permanent Works: Dharavi 

Base Slab: Scope - 250 M, Total Progress - 217 M

Concourse Slab: Scope - 250 M, Total Progress - 124 M

Roof Slab: Scope - 250 M, Total progress - 68 M

Platform Slab: Scope - 250 M, Total progress - 0 

Permanent Works: Santacruz

Base Slab: Scope - 252 M, Total Progress - 183 M

Concourse Slab: Scope - 252 M, Total Progress - 84 M

Roof Slab: Scope - 252 M, Total progress - 30 M

Platform Slab: Scope - 252 M, Total progress - 0

4Secant Piling Progress 

Dharavi

North retrieval & Ancillary: Scope - 307 Completed

Station Box: Scope - 779 Completed

Decking Piles-King Post (Interconnection): Scope - 52 Completed

BKC

North launching shaft: Scope - 180 Completed

Station Box: Scope - 1155 Completed

South Launching: Scope - 185 Completed

Decking Piles: Scope - 6 Completed

Entry/Exit-15-19-East(E10): Scope - 76 Completed

Entry/Exit-15-19-East(E11): Scope - 121 Completed

Entry/Exit-15-19-East(E05): Scope - 292, Total Progress - 186

Entry/Exit-15-19-East(E02): Scope - 176, Total Progress - 104

Vidyanagari

North launching shaft: Scope - 176 Completed

Station Box: Scope - 894 Completed

Santacruz

Secant pile: Scope - 585 Completed

Micro pile(station box): Scope - 2182 Completed

Secant pile-(ent/ext)-South: Scope - 163, Total Progress - 119

Secant pile-(ent/ext)-North: Scope - 112, Total Progress - 112

Micro pile(ent/exit): Scope - 468, Total progress - 194

Secant Pile(Ent/Ext)-North West: Scope - 464 , Total Progress - 220

Secant Pile(Ent/Ext)-South West: Scope - 252, Total Progress - 74

Secant Pile (Ent/Ext) East: Scope - 291, Total Progress - 62

MVS

Secant Pile: Scope - 184 Completed

5Rehabilitation & Resettlement 

__________

6Building condition Survey

__________

7Tree Cutting/transplantation

Dharavi

Tree Cutting - Scope - 5, Total Progress - 5, Remarks - Completed

Tree Transplant - Scope - 43, Total Progress - 31, Remarks - Ongoing

BKC

Tree Cutting - Scope - 67, Total Progress - 53, Remarks - Ongoing

Tree Transplant - Scope - 40, Total Progress - 24, Remarks - Ongoing

Vidyanagari

Tree Cutting - Scope - 47, Total Progress - 42, Remarks - Ongoing

Tree Transplant - Scope - 69, Total Progress - 54, Remarks - Ongoing

Santacruz

Tree Cutting - Scope - 7, Total Progress - 7, Remarks - Completed

Tree Transplant - Scope - 23, Total Progress - 21, Remarks - Ongoing

8

Traffic Diversion 

BKC Station – 220 m completed out of 220 m.

Vidyanagri Station – 70 m completed out of 710 m.

 

9
Geo-technical investigation

Vidyanagari Station - Completed

BKC Station - Completed

Santacruz Station - Completed

Dharavi Station - Completed

10Barricading

Vidyanagari Station - This Week - 0 ,Total progress - 382 ,Scope - 446

BKC Station - This Week - 0 ,Total progress - 357 ,Scope - 767

Santacruz Station - This Week - 0 ,Total progress - 517 ,Scope - 600 

Dharavi Station - This Week - 0 ,Total progress - 235 ,Scope - 339

Casting Yard - This Week - 0 ,Total progress - 153 ,Scope - 432