Weekly progress report for package-6

Updated as on: 15th Mar 2020

Sr. NoNature of WorkStatus
1Tunneling & Segment Production Progress 

CSIA T2 Metro Station

Tunnel CSIA T2 to Sahar Road Station (Downline):

Permanat Ring: Total Progress - 491, Scope - 491

Completed

Permanat Ring: Total Progress - 491, Scope - 491

Completed

Tunnel MVS to CSIA T1 (Upline):

Permanat Ring: Total Progress - 910, Scope - 910

Completed

Tunnel MVS to CSIA T1 (Downline):

Permanat Ring: Total Progress - 890, Scope - 892

Completed

Sahar Road Station to CSMIA
Domestic Airport Station (Downline)

Permanat Ring: Total Progress - 320, Scope - 1080

Segment Production Progress:

Permanent Rings: Total progress - 4625, Scope - 5016

2Excavation 

CSIA T1 Metro station

 Total progress - 274960 Cum. Scope - 275000 Cum. (Work in progress)

Sahar road Station

Total progress - 336961 Cum. Scope - 347191 Cum. (Work in progress)

CSIA T2 Metro Station

Total progress - 470060 Cum. Scope - 472000 Cum. (Work in progress)

3Base Slab Progress 

CSIA T1 Metro station:

Base slab completed.

Concourse Slab:  Total progress - 187.53 m. Scope - 272.5 m. (Work in progress)

Concourse to Roof Slab:  Total progress - 251.1 m. Scope - 463 m. (Work in progress)

Roof Slab:  Total progress - 122.56 m. Scope - 272.5 m. (Work in progress)

CSIA T2 Metro Station: 

Base Slab: Total progress - 292.8 m. Scope - 312.9 m. (Work in progress)

Concourse Slab:  Total progress - 206 m. Scope - 464.9 m. (Work in progress)

Concourse to Roof Wall:  Total progress - 165.2 m. Scope - 706 m. (Work in progress)

Roof Slab:  Total progress - 71.6 Cum. Scope - 493.9 m. (Work in progress)

Sahar Road Metro station: 

Base Slab: Completed

Concourse Slab:  Total progress - 198.6 m. Scope - 393 m. (Work in progress)

Concourse to Roof Slab:  Total progress - 214.5 m. Scope - 557 m. (Work in progress)

Roof Slab:  Total progress - 191 Cum. Scope - 393 m. (Work in progress)

4Secant Piling Progress 

CSIA T1 Metro station

Secant piles: Total progress - 808, Scope - 808

Micro piles: Total progress - 154, Scope - 154

Sahar road Station

Secant piles: Total progress - 1121, Scope - 1121

Subway secant piles: Total progress - 67, Scope - 67

CSIA T2 Metro Station

Secant piles: Total progress - 1298, Scope - 1298

5Rehabilitation & Resettlement 

______

6Building condition Survey

Pre-condition survey this week - 1

Total Progress - 60

Scope - 60

7Tree Cutting/transplantation

CSIA T1 -  Total progress - 3 , Scope - 3 ,  Completed

Transplantation - 59 out of 112

Sahar Rorad - Total progress - 4 , Scope - 4 , Completed

Transplantation - 177 out of 226

CSIA T2 - Total progress - 0 , Scope - 0 , Completed

Transplantation -  4 out of 4 completed

8Traffic Diversion

SAHAR ROAD STATION:

Road diversion: Stage-1 Completed

Subway completed

Sahar Shadow Road:

Commissioned on 27th July 2018.

Caping beam & Flood Wall: Completed

CSIA T2 Metro Station:

Internal Road: Completed.

Ancillary Works for TBM Launching: Completed

9Geo-technical investigation

SAHAR Road Metro station

Completed

Sahar Road to International Station

BHT-26,27 near hutment
area ,Not posiible.

CSIA T1 Metro Station

Completed

CSIA T2 Metro Station

Completed

10Barricading

SAHAR Road Metro station

All construction Works is going on within
secured barricading area .

CSIA T1 Metro station

Completed

CSIA T2 Metro station

Completed

Construction Depot JVLR (GI Sheets)

Completed