Weekly progress report for package-7

Updated as on: 20th Sep 2020

Sr. NoNature of WorkStatus
1Tunneling & Segment Production Progress 

Wainganga-1

Drive-1 (From Pali ground to CSIA-T2) (UpLine) -

Completed 1262rmt, Made Breakthrough on 24/09/2018.

Drive-2 (From Pali Ground to SEEPZ) (UpLine)-

Completed1689rmt, Made Breakthrough on 27/09/2019.

Wainganga-2:

Drive-1 (From Sariputnagar Ramp to SEEPZ) (DownLine)-

Completed 568rmt, Made breakthrough on 26/12/2018

Drive-2 (From Pali Ground to SEEPZ) (DownLine)-

Completed 1675rmt, Made Breakthrough at MIDC station on 12/12/2019

Wainganga-3:

Drive-1 (From Pali Ground to CSIA-T2) (DownLine)-

Completed 1313rmt, Made breakthrough on 13/02/2019

Drive-2 (From Sariputnagar Ramp to SEEPZ) (UpLine)-

Completed 572rmt, Made breakthrough on 13/08/2019

Segment Production PRogress:

100% of total completed.

2Excavation 

Station Box area:

Marol Naka: 100% completed

MIDC: 100% completed

SEEPZ: 100% completed

Ramp: 100% completed (including Cut & Cover and shaft area) 

3Base Slab Progress 

Marol Naka: 100%  Completed 

MIDC: 100% Completed

SEEPZ: 100% Completed

 Concourse Slab

Marol Naka: 173rmt completed out of 188rmt.

MIDC: 100% Completed

SEEPZ: 214.5rmt completed out of 240rmt

Roof Slab

Marol Naka: 137.7rmt completed out of 188rmt.

MIDC: 100% completed

SEEPZ: 18rmt completed out of 240rmt.

Mezzanine slab

Marol Naka: 176.2rmt completed out of 190rmt.

4Secant Piling Progress 

Marol Naka: 100% completed

MIDC: 100% completed

SEEPZ: 100% completed

Ramp: 100% completed (including Cut & Cover and shaft area)

5Rehabilitation & Resettlement 

_______

6Building condition Survey

Completed.

7Tree Cutting/transplantation

Marol: Tree Cutting: 7/9, Tree Transplantation: 42/50

MIDC: Tree Cutting: 9/11, Tree Transplantation: 90/130

SEEPZ: Tree Cutting: 9/12, Tree Transplantation: 84/115

 

8Traffic Diversion

Marol Naka: 100% Completed

MIDC: 100% Completed.

SEEPZ: 100% Completed.

9Geo-technical investigation

100% Completed

10Barricading

All the acquired area 100% barricaded.