Land Requirement

Sr. No. Permanent Land RequiredTemporary Land Required
PvtGovt. / Semi Govt.PvtGovt. / Semi Govt.
1Station and allied facilities (MCGM, Home Dept, MHADA, PWD, etc.)0.55 ha8.70 ha2.90 ha12.00 ha
2Traction Sub-Station (at 3 locations)-0.60 ha--
3Construction Depot (12 pockets)0.55 ha8.70 ha2.90 ha12.00 ha
4TBM worksites (12 pockets)---7.00 ha
5Casting yard (7 packages)*---35.00* ha
6Other allied & commercial uses-3.72 ha--
 Total0.55 ha13.02 ha2.90 ha62.20 ha

Total Land Required: 78.67 ha

Permanent: 13.57 ha

Temporary: 65.10 ha

Pvt: 3.45 ha

Govt: 75.22 ha

  • Private land acquisition is being done under sec126 of MRTP Act 1966 by negotiation to the extent possible.
  • MMRCL has set up Preliminary Hearing Committee to hear the suggestions and objectives.
  • Compensation Committee is also set up under the Chairmanship of former IAS officer Shri Sudhir Thakare.