Project Status

The MML-3 Project is divided into 18 main packages of ‘Project’ & ‘System’ wings.

Package wise status of the project is as under:

Packages Nature of Work Name of Contractor Amt Status Target for Contract Award
Package 1 Civil Works – Tunnels & Stations L&T-STEC JV Rs. 2,988.53 cr Letter of Acceptance Issued to Contractor Awarded
Package 2 Civil Works – Tunnels & Stations HCC-MMS JV Rs. 2,521.89 cr Letter of Acceptance Issued to Contractor Awarded
Package 3 Civil Works – Tunnels & Stations M/S DOGUS-SOMA Rs. 2,557.84 cr Letter of Acceptance Issued to Contractor Awarded
Package 4 Civil Works – Tunnels & Stations M/S CEC-ITD CEM-TPL JV Rs. 2,830.10 cr Letter of Acceptance Issued to Contractor Awarded
Package 5 Civil Works – Tunnels & Stations M/S J. Kumar-CRTG Rs. 2,817.02 cr Letter of Acceptance Issued to Contractor Awarded
Package 6 Civil Works – Tunnels & Stations M/S J.Kumar-CRTG Rs. 2,118.40 cr Letter of Acceptance Issued to Contractor Awarded
Package 7 Civil Works – Tunnels & Stations L&T-STEC JV Rs. 2,281.45 cr Letter of Acceptance Issued to Contractor Awarded
Package 8 Civil – Depot SAM (INDIA) BUILTWELL PVT LTD Rs. 328.26 cr Letter of Acceptance Issued to Contractor Awarded
Package 9 Plant & Equipment for Depot - - DPR Review/Design work for ‘PQ Preparation’ for System Bids started. May, 2017
Package 10 Track Works - - DPR Review/Design work for ‘PQ Preparation’ for System Bids started. May, 2016
Package 11 Traction - - Bids opened on 02.08.17 for package 11B and on 04.08.17 for package 11A Aug, 2017
Package 12 Signaling, Train control, PSD & Communications - -

JICA NOC for Part-1 & Part-3 of STPT RFP received on 16-06-2017

Part-1 & Part-3 RFP of STPT submitted to re-approval of JICA on 12-07-2017

Part-2 & Part-4 of STPT RFP under Finalization

Dec, 2017
Package 13 Station Security System - - - -
Package 14 Automatic Fare Collection - - PQ Bid opened on 20/03/2017 evaluation under process. Dec, 2017
Package 15 Tunnel Ventilation & Environmental Condition System - -

Pre-Qualification completed.

RFP issued to Pre-qualified bidders on 07.02.17.

Bids are scheduled for opening in August’ 17.

Nov, 2017
Package 16 Lifts & Escalators - - PQ bids opened on 08.05.17 and Evaluation under progress. Feb, 2018
Package 17 Rolling Stock - -

PQ document submission & opening was successfully conducted on 20th June, 2017

Total Six (6) number of RS bidders participated for Rolling Stock (Package-17)

PQ Evaluation is under progress

Nov, 2017
Package 18 General Consultant - - General Consultants engaged. May, 2016