Project Status

The MML-3 Project is divided into 18 main packages of ‘Project’ & ‘System’ wings.

Package wise status of the project is as under:

Packages Nature of Work Name of Contractor Amt Status Target for Contract Award
Package 1 Civil Works – Tunnels & Stations L&T-STEC JV Rs. 2,988.53 cr Letter of Acceptance Issued to Contractor Awarded
Package 2 Civil Works – Tunnels & Stations HCC-MMS JV Rs. 2,521.89 cr Letter of Acceptance Issued to Contractor Awarded
Package 3 Civil Works – Tunnels & Stations M/S DOGUS-SOMA Rs. 2,557.84 cr Letter of Acceptance Issued to Contractor Awarded
Package 4 Civil Works – Tunnels & Stations M/S CEC-ITD CEM-TPL JV Rs. 2,830.10 cr Letter of Acceptance Issued to Contractor Awarded
Package 5 Civil Works – Tunnels & Stations M/S J. Kumar-CRTG Rs. 2,817.02 cr Letter of Acceptance Issued to Contractor Awarded
Package 6 Civil Works – Tunnels & Stations M/S J.Kumar-CRTG Rs. 2,118.40 cr Letter of Acceptance Issued to Contractor Awarded
Package 7 Civil Works – Tunnels & Stations L&T-STEC JV Rs. 2,281.45 cr Letter of Acceptance Issued to Contractor Awarded
Package 8 Civil – Depot SAM (INDIA) BUILTWELL PVT LTD Rs. 328.26 cr Letter of Acceptance Issued to Contractor Awarded
Package 9 Plant & Equipment for Depot - - Tender documents under preparation. -
Package 10 Track Works - - PQ bids are under finalization. Nov, 2017
Package 11 Traction & Power Supply - -

Pre-Qualification completed for 11A & 11B

RFP Bids opened on 04. 08.17 for 11A & on 02.08.17 for 11B

Technical Evaluation completed and submitted to JICA for NOC.

Nov, 2017
Package 12 Signaling, Train control, PSD & Communications - -

RFP issued to Pre-qualified bidders on 22.07.17.
Bids scheduled to be submitted and opened on 24.10.17.

Dec, 2017
Package 13 Station Security System - - - -
Package 14 Automatic Fare Collection - - Pre-qualification completed. 
AFC Bid Documents Part 1 & 3 submitted for approval of JICA on 02.08.17.
Dec, 2017
Package 15 Tunnel Ventilation & Environmental Control System - -

Pre-Qualification completed.

RFP Bids opened on 1.09.17.

Technical Bid Evaluation under progress

Nov, 2017
Package 16A Escalator Works - -

Pre-Qualification completed

RFP issued to Pre-Qualified bidders on 29.09.17.

Bids are scheduled for opening on 28.12.17.

Mar, 2018
Package 16B Elavator/Lift Works - -

Pre-Qualification completed.

RFP issued to Pre-Qualified bidders on 04.09.17.

Bids are scheduled for opening 30.11.17.

Mar, 2018
Package 17 Rolling Stock - -

Pre-Qualification completed.

RFP issued to Pre-qualified bidders on 3rd October 2017.

Bids are scheduled for opening on 18th December 2017.

Mar, 2018
Package 18 General Consultant - - General Consultants engaged. May, 2016

The MML-3 Project is divided into 18 main packages of ‘Project’ & ‘System’ wings.

Package wise status of the project is as under:

Packages Nature of Work Name of Contractor Amt Status Target for Contract Award
Package 1 Civil Works – Tunnels & Stations L&T-STEC JV Rs. 2,988.53 cr Letter of Acceptance Issued to Contractor Awarded
Package 2 Civil Works – Tunnels & Stations HCC-MMS JV Rs. 2,521.89 cr Letter of Acceptance Issued to Contractor Awarded
Package 3 Civil Works – Tunnels & Stations M/S DOGUS-SOMA Rs. 2,557.84 cr Letter of Acceptance Issued to Contractor Awarded
Package 4 Civil Works – Tunnels & Stations M/S CEC-ITD CEM-TPL JV Rs. 2,830.10 cr Letter of Acceptance Issued to Contractor Awarded
Package 5 Civil Works – Tunnels & Stations M/S J. Kumar-CRTG Rs. 2,817.02 cr Letter of Acceptance Issued to Contractor Awarded
Package 6 Civil Works – Tunnels & Stations M/S J.Kumar-CRTG Rs. 2,118.40 cr Letter of Acceptance Issued to Contractor Awarded
Package 7 Civil Works – Tunnels & Stations L&T-STEC JV Rs. 2,281.45 cr Letter of Acceptance Issued to Contractor Awarded
Package 8 Civil – Depot SAM (INDIA) BUILTWELL PVT LTD Rs. 328.26 cr Letter of Acceptance Issued to Contractor Awarded
Package 9 Plant & Equipment for Depot - - Tender documents under preparation. -
Package 10 Track Works - - PQ bids are under finalization. Nov, 2017
Package 11 Traction & Power Supply - -

Pre-Qualification completed for 11A & 11B

RFP Bids opened on 04. 08.17 for 11A & on 02.08.17 for 11B

Technical Evaluation completed and submitted to JICA for NOC.

Nov, 2017
Package 12 Signaling, Train control, PSD & Communications - -

RFP issued to Pre-qualified bidders on 22.07.17.
Bids scheduled to be submitted and opened on 24.10.17.

Dec, 2017
Package 13 Station Security System - - - -
Package 14 Automatic Fare Collection - - Pre-qualification completed. 
AFC Bid Documents Part 1 & 3 submitted for approval of JICA on 02.08.17.
Dec, 2017
Package 15 Tunnel Ventilation & Environmental Control System - -

Pre-Qualification completed.

RFP Bids opened on 1.09.17.

Technical Bid Evaluation under progress

Nov, 2017
Package 16A Escalator Works - -

Pre-Qualification completed

RFP issued to Pre-Qualified bidders on 29.09.17.

Bids are scheduled for opening on 28.12.17.

Mar, 2018
Package 16B Elavator/Lift Works - -

Pre-Qualification completed.

RFP issued to Pre-Qualified bidders on 04.09.17.

Bids are scheduled for opening 20.11.17.

Mar, 2018
Package 17 Rolling Stock - -

Pre-Qualification completed.

RFP issued to Pre-qualified bidders on 3rd October 2017.

Bids are scheduled for opening on 18th December 2017.

Mar, 2018
Package 18 General Consultant - - General Consultants engaged. May, 2016
Top