Project Status

The MML-3 Project is divided into 18 main packages of ‘Project’ & ‘System’ wings.

Package wise status of the project is as under:

Packages Nature of Work Name of Contractor Amt Status Target for Contract Award
Package 1 Civil Works – Tunnels & Stations L&T-STEC JV Rs. 2,988.53 cr Letter of Acceptance Issued to Contractor Awarded
Package 2 Civil Works – Tunnels & Stations HCC-MMS JV Rs. 2,521.89 cr Letter of Acceptance Issued to Contractor Awarded
Package 3 Civil Works – Tunnels & Stations M/S DOGUS-SOMA Rs. 2,557.84 cr Letter of Acceptance Issued to Contractor Awarded
Package 4 Civil Works – Tunnels & Stations M/S CEC-ITD CEM-TPL JV Rs. 2,830.10 cr Letter of Acceptance Issued to Contractor Awarded
Package 5 Civil Works – Tunnels & Stations M/S J. Kumar-CRTG Rs. 2,817.02 cr Letter of Acceptance Issued to Contractor Awarded
Package 6 Civil Works – Tunnels & Stations M/S J.Kumar-CRTG Rs. 2,118.40 cr Letter of Acceptance Issued to Contractor Awarded
Package 7 Civil Works – Tunnels & Stations L&T-STEC JV Rs. 2,281.45 cr Letter of Acceptance Issued to Contractor Awarded
Package 8 Civil – Depot - - State Government's decision on Depot Site is Awaited -
Package 9 Plant & Equipment for Depot - - DPR Review/Design work for ‘PQ Preparation’ for System Bids started. May, 2017
Package 10 Track Works - - DPR Review/Design work for ‘PQ Preparation’ for System Bids started. May, 2016
Package 11 Traction - - Bid opening date 15/06/2017 for 11B & 19/06/2017 for 11A Aug, 2017
Package 12 Signaling, Train control, PSD & Communications - - Prequalification of Applicants - 05 Nos. finalized on 28/12/2016 Bid Documents submitted for JICA concurrence on 16/02/2017 Dec, 2017
Package 13 Station Security System - - - -
Package 14 Automatic Fare Collection - - PQ Bid opened on 20/03/2017 evaluation under process. Dec, 2017
Package 15 Tunnel Ventilation & Environmental Condition System - - Bid Opening date 23/06/2017 Aug, 2017
Package 16 Lifts & Escalators - -

PQ document opening was successfully conducted on 8/05/2017

Total 08 number of bidders participated fo Package 16A(Escalators)

Total 07 number of bidders participated fo Package 16B(Lifts/Escalators)

Evaluation of the document is in progress

Feb, 2018
Package 17 Rolling Stock - -

PQ document submission & opening was successfully conducted on 20th June, 2017

Total Six (6) number of RS bidders participated for Rolling Stock (Package-17)

PQ Evaluation is under progress

Nov, 2017
Package 18 General Consultant - - General Consultants engaged. May, 2016