Photo Gallery

    • Casting of 1st tunnel segment Casting Yard
    • EOT crane commissioning Casting Yard
    • Median demolition Acharya Attre
    • Secant Piling Mumbai Central
    • Secant Piling Mahalaxmi
    • Steel cage fabrication for secant piling Mumbai Central
    • Street pole removal Mahalaxmi
    • Street pole removal Worli
    • SWD diversion Science Museum
    • Utility trenching Worli
    • Utility trenching Acharya Attre
    • Batching plant area fencing Casting Yard
    • EOT crane commissioning Casting Yard
    • Gantry crane alignment work Casting Yard
    • Median demolition Science Museum
    • Monsoon prepardness Mumbai Central
    • Root ball preparation tree transplantation Worli
    • Secant Piling Mumbai Central
    • Secant Piling Science Museum
    • Secant Piling Worli
    • Segment mould alignment work Casting Yard
    • SWD diversion Science Museum
    • Utility Trenching Acharya Attre Chowk
    • Utility Trenching Worli
    • Utility Trenching Mumbai Central
    • Geo - technical investigation Mahlaxmi
    • Secant Piling Mahalaxmi
    • Utility Diversion Science Museum
    • Utility investigation Science Museum
    • Secant Piling Worli
    • Secant Piling Mumbai Central
    • Utility Investigation Mumbai Central
    • Barricade Cleaning Acharya Attre Chowk
    • Barricade Paintaing Mumbai Central
    • Tree Cutting Acharya Attre
    • Utility Investigation
    • Casting Yard
    • EOT crane fikxing Casting Yard
    • Median demolition Science Museum
    • Road widening for traffic diversion Worli
    • Secant Piling Mahalaxmi
    • SWD diversion Science Museum
    • Test pile Acharya Attre
    • Tree transplantation on Science Museum
    • Utility Investigation Mahalaxmi
    • Factory shed side sheet fixing - Casting Yard
    • Secant Piling Science Museum
    • Road widening Worli
    • Secant Piling Mumbai Central
    • Secant Piling Science Museum
    • SWD dikversion Science Museum
    • Test pile Acharya Attre
    • Test Pile Mahalaxmi
    • Test Pile Worli
    • Tree transplantation at Mahalaxmi
    • Tree transplantation Mumbai Central.
    • Labour rest room establishment- Casting Yard
    • Labour rest room shed work  - Acharya Attre
    • Canteen establishment at Casting Yard
    • Drain chambers cleaning Worli
    • Drain chambers cleaning Acharya Attre
    • geotechnical investigation- Tunnel between Mahalaxmi and Mumbai Central
    • MMRC office construction depot
    • Monsoon prepardness work - Mumbai Central
    • Monsoon prepardness work - Worli
    • Road widening work Worli
    • Secant piling Mumbai Central
    • Secant piling Science Museum
    • Secant piling Mahalaxmi
    • SWD diversion Science Museum
    • Factory shed side sheet fixing Casting Yard
    • Tree cutting Science Museum
    • Tree cutting Mumbai Central
    • Backfilling of utility trenches Science Museum
    • Brickwork at Casting Yard
    • Drain chamber cleaning - Mahalaxmik
    • MMRC site office construction- construction depot
    • Secant piling Mumbai Central
    • Secant piling Mahalaxmi
    • Sheet fixing - factory shed - Catsing Yard
    • SWD diversion Science Museum
    • Utility investigation Worli
    • Aerial view Science Museum
    • Drain work Casting Yard
    • Factory shed roof erection Casting Yard
    • GC and MMRC office setup construction depot
    • Gantry crane erection Casting Yard
    • Secant piling Mahalaxmi
    • Secant piling Mumbai Central
    • Utility Trenching Acharya Attre Chowk
    • SQD diversion Science Museum
    • Tree cutting Acharya Attre Chowk
    • Wheel wash bay Casting Yard
    • Barricade fixing Mumbai Central
    • Gantry crane erection  - Casting Yard
    95
    Package - 3
    24/07/2017
    • Piling Work at Domestic Station
    • Waler beam fabrication at Sahar Road Station
    • Factory Shed at Casting Yard
    • Erected Gantry at Casting Yard
    • Stacking area at Casting Yard
    • Tree Transplantation at Domestic Station
    • 2.Tree Transplantation at Domestic Station
    • Anchoring at Sahar Road Station
    • Road Work at International Station
    • Segment Stacking Area at Casting Yard-min
    • Caping Beam Construction in Receiving Shaft at International Station
    • Electric Room at Domestic Station
    • Wheel Wash Bay at International Station-min
    • Excavation at Sahar Road Station
    • Factory Shed at Casting Yard-min
    • Road Work at International Station
    • Factory Shed at  Casting Yard
    • GC-MMRC Project office at International Station
    • JV Project Office at International Station
    • Launching Shaft at Sahar Road Station
    • Secant piling at Domestic Station
    • Site Office at Casting Yard
    • Stacking Area at Casting Yard
    • Wheel Wash Bay at Domestic Station
    • Wheel Wash Bay  at International Station
    • Backfilling on 1800mm Pipe
    • Fabrication of Sedimentation Tank
    • Factory Shed at Casting Yard
    • Labour Camp  at Construction Depot
    • Wheel Wash Bay
    • Gantry Erection at Casting Yard
    • Road work at Casting Yard
    • GC Office Foundation work
    • Project office work
    • Piling at Sahar Road Station
    • Piling Muck Disposal
    • Batching Plant erection at Casting Yard
    • Project Office Construction at International Station
    • Factory Shed erection at Casting Yard
    • Flood protection wall at Sahar Road Station
    • Labour camp Construction in progress at Construction Depot
    • Labour colony construction at Casting Yard
    • Piling work at International Station
    • Piling work at International Station
    • Bacfilling Near factory shed at casting yard
    • Barricade fixing at CISF for underground Watertank at Sahar Road Station
    • Barricade Removing And Fixing Work For Road Diversion
    • Wheel wash Bay at Sahar Road Station
    • Factory shed foundation at Casting Yard
    • Flood Protection Wal Construction at Sahar Road Station
    • Project Office construction in progress at International Station
    • Road Work in progress at Domestic Station
    • Sapling Distribution at Domestic Station
    • Subway area Land Devlopement for barricade fixing at Sahar Road Station
    • Raft Breaking in secant pile area at Domestic Station
    • Drilling for test anchoring at Sahar Road Station
    • Waler fixed for test anchoring at Sahar Road Station
    • Secant pile concrete work  at Domestic Station
    • Stacking yard foundtion PCC at Casting Yard
    • Factory Shed erection at Casting Yard
    • Capping beam at Sahar Road Station
    • Batching Plant at Casting Yard
    • Cement Stacking Shed at Construction depot
    • Weigh bridge at Construction Depot
    • Wheel wash bay functional at Sahar Road Station
    • BHT-10 Machin satlltion work  at Domestic Station
    • Batching Plant Foundation Work at Casting Yard
    • Capping Beam Reinforcement Binding at Sahar Road Station
    • Containers for project Office at International Station
    • Utility identification  at Domestic Station
    • Factory Shed Column Painting at casting Yard
    • Factory Shed Area Rail fixing in progress at casting Yard
    • Light pole fixing work  at Domestic Station
    • Stacking Area at Casting Yard
    • Factory Shed Foundation work at Casting Yard
    • Rail line fixing at Casting Yard
    • Pile Cage Making in progress at International Station
    • Utility identification  at Domestic Station
    • Piling Work at Internatioanal Station
    • Probe Hole-12 Drilling in Progress at International Station
    • Batching Plant Foundation at casting yard
    • Gantry line-03 at Casting Yard
    • Green Net fixing
    • Labour rest room at international Station
    • Labour toilets construction at Casting yard
    • Weigh Bridge at casting yard
    • Pile Concreting at International Station
    • Pipe And Plate welding for green net
    • Probehole work in progress at International Station
    89
    Package - 6
    23/07/2017
    • Installation of noise barrier to reduce inconvenience to residents
    • Implementation of Traffic Diversion at Jamshedji Tata road
    • Pathway for pedestrians at Jamshedji Tata road
    • Commencement of piling at Churchgate Station
    • Calibration of Batching Plant (60 Cu.m/hr)
    • Third party inspection of Piling Rigs
    • Soldier Pile for trench preparation for pipe jacking
    • Providing safe and clean access to pedestrians
    • Installation of Noise Barriers near residential buildings
    • Progress review at Vidhan Bhavan Station
    • MMRC MD visits Station Cuffe Parade
    • MMRC MD 's visit at Hutatma Station
    • Project review by MMRC MD
    • Plunge column works at DN Road
    • North bound traffic closure at Captain Prakash Pethe Marg for Utility Diversion
    • Induction to workmen using Audio-Visual Aid
    • Regular cleaning of roads
    • Signages for effective implementation of Traffic Diversion
    • Introducing new signage for pedestrians
    • Paintaing new pedestrian crossing after implementing Traffic Diversion at Capt. Prakash Pethe Marg
    • Rig arrives at Churchgate for commencement of Piling
    • 2nd rig commissioned at Vidhan Bhavan Station
    • Vibration Monitoring at Heritage Building
    • Regular Briefing to Guards
    • Briefing to 40 Traffic Marshalls by Safety Manager
    • Fabrication of Traffic Decking
    • Project information board at Station Locations
    • Keeping roads clean by constructing wheel-wash bay at all work areas.
    • Erection of 3rd Batching Plant at MIDC land in Colaba
    • Pipes laid to drain rain water
    • Safe access  for pedestrians
    • Structural steel fabrication for road decking
    • Sapling distribution on World Environment Day
    • Engineer's Construction Manager  Mr. Evan Chan planting sapling at casting yard during  World Environment Day
    • Celebration of World Environment Day
    • Thanking Mumbaikar's for co-operation
    • Thanking Mumbaikar's for co-operation
    • Bun wall constructed behind barricade boards to prevent water flowing into road
    • Managing smooth flow of traffic
    • Keeping work area dry during rains
    • Preventing flooding of roads during rains
    • Raincoat provided to workmen
    • Third Batching plant under erection at MIDC Land
    • Second rig arriving at Vidhan Bhavan for piling works
    • Batching plant erection at MIDC land
    • Preparing paved access beside work area for local residents.
    • Piling at Hutatma chowk
    • Traffic diversion at DN Road
    • Visit by JICA officials
    • Piling rig for Hutatma chowk station
    • Piling commences at Hutatma Chowk
    • Tree Transplantation at Aarey Colony
    • Tree Transplantation at Aarey Colony
    • Tree Transplantation at Aarey Colony
    • Inspectioln of trees by MCGM officers
    • Newly planted trees at Aarey Colony
    • Alertness around work area  - L&T-STEC staff extinguishing  fire from a vehicle  in vicinity of work site
    • Guidewall for piling at Hutatma Chowk
    • Piling rig for Hutatma Chowk
    • Implementation of traffic diversion at  Hutatma Chowk station
    • North bound traffic blocked at DN Road to start piling at Hutatma Chowk
    • Traffic diversion at Hutatma Chowk
    • Trial rings
    • Tunnel segment ring inspection
    • Biometric attendance for supervisors
    • Visit of DCP Traffic to station sites
    • Footpath restored back to original condition after cable diversion at Cuffe Parade
    • Hon'ble Chief Minister of Maharashtra at Cuffe Parade  station site.
    • Station manager taking lead at safety tool box talk
    • Public interaction and awareness for Building owners at DN road
    • Standard safety practice of L&T - STEC: Caps of pile reinforcement
    • Demolition of buildings at Vidhan Bhavan
    • Demolition of buildings at Vidhan Bhavan
    • Earth day celebrations
    • Tunnel ring assembled
    • Dimension check of pre-cast moulds by the Engineer (MAPLE)
    • Public interaction and awareness meet for owners of building at DN Road
    • Awareness talk to workman on Hepatitis by Dr. Fadia
    • Visit of Joint CP(Traffic) at Hutatma Chowk
    • Visit of Joint CP(Traffic) at Vidhan Bhavan
    • Visit of Joint CP(Traffic) at Churchgate
    • Lighting on barricades and seperate walkways for pedestrians
    • Road cleaning at Station vicinity at the end of day
    • CSR Activity - Distribution of saplings at DN Road
    • CSR Activity - Sapling distribution event at DN Road
    • Maintainance of newly planted trees at Aarey Colony
    • Piling in progress at Cuffe Parade
    • Station Manager taking lead at Safety Tool box talk
    • Regular cleaning of roads in vicinity of works area
    • Trial run for traffic diversion at service road in front of Taj Vivanta
    • Materials being unloaded at Traffic Police Headquarters
    • Inaugration of precast yard on 29/03/2017
    • Inaugration of Casting Yard by Managing Director of MMRCL
    • Director (Projects) inaugrating Casting Yard
    • Executive Director (Planning) inaugrating Casting Yard
    • Moulds for Segment Casting
    • Pouring of concrete for precasts segment
    • Removal of segments from moulds
    • Shifting of casted segment from mould to stacking frame
    99
    Package - 1
    23/07/2017
    • Nayanagar Excavation
    • Nayanagar Excavation
    • Nayanagar Excavation
    • Casting Yard segment casting
    • Casting Yard stacking bay
    • Bus queue shelter shifting
    • Shitladevi transplantation
    • Aarey transplantation
    • Nayanagar
    • Siddhivinayak
    • Siddhivinayak
    • Dadar traffic diversion
    • Dadar tree cutting
    • Dadar Utility Diversion
    • Shitladevi road works
    • Casting Yard - Segment casting
    • Dadar road works
    • Dadar & Shitladevi road works
    • Nayanagar micro pile gantry foundation
    • Nayanagar shaft excavation
    • Nayanagar shaft excavation
    • Capping beam Nayanagar
    • Casting Yard moulds
    • Casting Yard
    • Dadar house keeping
    • Nayanagar Micropile
    • Dadar road widening
    • Ravindra Natya Mandir
    • Casting Yard Gantry Foundation
    • Casting Yard segment
    • Dadar road
    • Siddhivinayak piling
    • Siddhivinayak piling
    • Dadar road widening
    • Casting Yard cage preparation
    • Shitladevi Road Excavation
    • Siddhivinayak
    • Siddhivinayak cage building
    • Shitladevi Road Widening
    • Siddhivinayak piling
    • Capping Beam at Nayanagar
    • Road Wideniing works at Dadar
    • Road Widening works at Dadar & Shitladevi
    • Segment Casting Yard
    • Segment Yard
    • Casting Yard
    • Nayanagar
    • Siddhivinayak
    • Sapling Distribution - Project Neighbourhood
    • Tree distribution in Project Neighbourhood
    • Tree Neighbourhood program
    • Project Neighbourhood
    • Tree Plantation
    • Casting Yard Batching Plant setup
    • Casting Yard 1st Segment Demoulding
    • Casting Yard 1st Segment Demoulding
    • Nayanagar Piling Works
    • Nayanagar
    • Casting Yard National Safety Week
    • Casting Yard National Safety Day
    • Safety Week Casting Yard
    • Casting Yard  Binding
    • Dadar site container
    • Dadar Utility Identification
    • Gantry erection Casting Yard
    • Gantry erection Casting Yard
    • Pilling works Siddhivinayak
    • Barricading at Naya Nagar
    • Barricading at Siddhivinayak
    • Footpath excavation Road Widening at Dadar
    • Guide wall at Siddhi Vinayak
    • Guide wall at Siddhi Vinayak
    • Public Information Center
    • Castin Yard factory
    • Casting Yard Silos arrived
    • Guide wall preparatory Works at Siddhivinayak
    • Naya Nagar Shaft piling work is in progress
    • Worli to Siddhivinayak soil investigation work
    • Barricading at Siddhivinayak
    • Casting Yard
    • MGL Utilities at Siddhivinayak
    • Nayanagar Shaft piling work
    • Nayanagar shaft piling work
    • Nayanagar Shaft Piling work
    • Pilling works at Nayanagar
    • Profile sheet fixing at Casting Yard
    • Rock sampling during soil investigation
    • Shaft piling work at Nayanagar
    • Sidhivianayak Rig calibration
    • Soil investigation work
    • Siddhivinayak Utility identification
    • SSV Utility identification
    • Geo-technical work at Shitladevi
    • Geo-technical work at Dadar
    • Footpath dismantling work at Dadar
    • Board painting work in progress
    • Barricades at Siddhivinayak
    • Nayanagar pile boring work
    • Nayanagar steel bending work
    • Nayanagar toilet work
    101
    Package - 4
    16/07/2017
    • Soil excavation and rock drilling work is in progress at Mid Shaft
    • Secant pile boring ins in progress at SEEPZ Station
    • Secant pile boring ins in progress at SEEPZ Station
    • Secant pile boring ins in progress at SEEPZ Station
    • Capping beam curing in progress at Marol Naka
    • Entrance area levelling work at Casting Yard
    • Excavated muck lifting from shaft at Mid Shaft
    • Gantry Crane erection work is in progress at Mid Shaft
    • Landscape work is in progress at Casting Yard
    • Rebar bending work is in progress at Ramp area
    • Rebar shed fabrication work is in progress at Casting Yard
    • Utility identification in MIDC Station
    • Wheel wash bay paintaing work is in progress at ramp area site
    • Backfilling and ground levelling work at ramp area
    • Existing SWD demolishing work at SEEPZ station
    • Muck shifting and ground improvement work at SEEPZ
    • Rebar cage fabrication work at SEEPZ station
    • Rebar shed PCC completed at Casting Yard
    • Segment ring stand fabrication work at Casting Yard
    • Shed fabrication work of hopper at Casting Yard
    • Primary pile casting at SEEPZ station
    • Spiral rebar bending drum at SEEPZ station
    • Primary pile casting at SEEPZ station
    • Wheel wash bay working at Mid shaft
    • Soil excavation and muck disposal work is in progress at Mid Shaft
    • Trial trench works in progress at SEEPZ station
    • Ring beam ready for 4th pour casting at mid shaft
    • Ring beam completed portion at mid shaft
    • Casting Yard shed service road work completed at Casting Yard
    • Drainage construction along periphery at Casting Yard
    • Secant pile boring work at Seepz Station
    • Drainage excavation work in Casting Yard
    • Rebar fixing at culvert Seepz
    • Earth filling work in progress at Seepz Station
    • Tunnel segment ring is in progress at Casting Yard
    • Rebar fixing work at sedimentation tank at Seepz
    • Tree plantation at Casting Yard
    • Rebar shed erection work in progress at Casting yard
    • Wheel wash bay work in progress at Seepz Station
    • Casting yard shed construction
    • Casting yard works in progress
    • Excavation at Mid Shaft
    • Ground improvement for piling at SEEPZ station
    • Rebar fixing in process for secant piling in Marol Naka
    • Secant Piling in Marol Naka
    • Shuttering for flood wall and crane foundation is in progress at Mid Shaft
    • Store shed construction in MIDC
    • Wheel wash bay Sedimentation tank construction in MIDC
    • Arial view of Mid Shaft area (Pali Ground)
    • Anchor bolts fixing for silo foundation in progress at Casting Yard
    • Boom lift & crane received at Casting Yard
    • Capping beam concrete
    • Capping work in progress in Mid shaft areas
    • Gantry wall shuttering work in progress
    • Casting shed structural steel painting work progress
    • Rebar shed fabrication work in progress
    • Retaining wall backfilling in progress at MIDC
    • Secant piling in progress at Marol Naka
    • Seepz existing boundary wall demolition
    • Store shed erection work in progress at Mid Shaft area (Pali Ground)
    • SWD 2mx2m top slab rebar work in progress at Seepz Station
    • Utility diversion in progress at Marol Naka
    • Capping beam work is in progress at Mid shaft area (Pali ground)
    • Curing Tank work in Progress at Casting Yard
    • Gantry pile work in progress at Mid Shaft area
    • Housekeeping work  near Gate No-2 at Pali ground
    • JV office work 100% completed at Mid Shaft area (Pali Ground)
    • Prestart breifing at Mid Shaft area (Pali ground)
    • QC Lab at Casting Yard
    • Prestart breifing at Seepz Station
    • SEEPZ security & NFCD joint inspection done for Demolition of Seepz boundary wall
    • Silo foundation work for Batching Plant work in progress at Casting Yard
    • Wall erection work for Gantry Foundation at Casting Yard
    • Wall erection work for Gantry foundation in progress at Casting Yard
    • Water sprinkling work in progress  at Casting Yard
    • Capping beam work is in progress at Mid Shaft area (Pali Ground)
    • Casting Shed Column work in progress at Casting Yard
    • Gantry Foundation work in progress at Casting Yard
    • Hutment removal in progress in Ramp area (2)
    • Hutment removal in progress in Ramp area
    • Labour Shed work in Progress at Mid Shaft area
    • Laying of Murum work in progress for Internal Road at Casting Yard
    • Piling work in progress at Marol Naka
    • Reliance substation shifting in progress at MIDC
    • Retaining wall construction in progress at MIDC
    • Saplings distribution at SEEPZ 1
    • Saplings distribution at SEEPZ 1
    • Sore Foundation work in Progress at Mid Shaft area
    • Waterline & SWD diversion in progress at Marol Naka
    • Casting Shed Column Curing work progress in at Casting Yard
    90
    Package - 7
    16/07/2017
    • BKC - North Launching Shaft
    • BKC Steel Yard - Batching Plant Erection Ongoing
    • BKC - Project Office
    • Vidyanagri - Piling (Gr 1 to 6 - West)
    • Dharavi - Pile Chipping for Capping Beam (Gr 1 to 6 - Nallah Side)
    • Dharavi - 2nd Piling Rig Mobilised
    • Vidya Nagari North Shaft - Pile Chipping for Capping Beam Preparation
    • Dharavi - Piling Activity at Gr 10-17 (Nallah Side)
    • Vidya Nagari - Piling Activity in North Shaft
    • Project office progress
    • Vidya Nagari - RCC work ongoing for Road Diversion
    • Tree cutting - Santacruz
    • Vidya Nagari North Shaft - Pile Chipping for Capping Beam Preparation
    • BKC - Capping Beam at North Launching Shaft
    • Dharavi - Piling at Grid 1-6 (West)
    • Vidyanagri - 1200 mm Water Line - Shutdown Preparation
    • Vidyanagri - Cable Anchor Insertion
    • BKC - Trial Run Traffic Diversion
    • Dharavi - Pile Concreting
    • Dharavi - Pile Concreting
    • Vidyanagri - 1200mm dia Water Line Encasing
    • Vidyanagri - Capping Beam
    • Vidyanagri - GSB for Road Diversion
    • Piling work ongoing at BKC Station
    • Piling work on going at Dharavi Station
    • Rig machine for GI shifted to Mid Ventillation Shaft
    • Welding and cutting work on going at Vidyanagari Station.
    • Cable Anchoring - Vidyanagri North Shaft
    • Piling - BKC North Shaft
    • Piling - Dharavi (Gr 1 to 6)
    • Project Office - BKC
    • Meter Room Brick Work on Going at BKC Station
    • Exacavation for Drain on going at Dharavi Station
    • Tench Work on going at Vidyanagari Station
    • Trench Excavation ongoing at Santacruz Station
    • Boring on going for TBH 19 at Santacruz Station
    • Boring on going for TBH 19 at Santacruz Station
    • RCC work at BKC Station for project office.
    • Utility Shifting work on going at Vidyanagari Station
    • Trial Pit Excavation at Santacruz Station
    • Foundation Footing Progress for Project Site office BKC Station
    • Piling work in progress at Vidyanagari Station
    • SBH 8 bore Hole in progress, East Side Highway, Santacruz Station
    • Utility wok in progress, Vidyanagari Station
    • Pile cage work in progress, Vidyanagari Station
    • Piling work in progress Vidyanagari Station
    • Pit excavation for Sewer line Diversion, BKC Station
    • Site Visit By Director of Project MMRC, BKC Station
    • Survey Work for SWD Line, Dharavi Station
    • Trial pit excavation for TBH 19, Santacruz Station
    • Bore Hole Work in Progress at Sanatacruz Station
    • Excavation work for Utility in progress at Vidyanagari Station
    • Foundation Footing RCC done at BKC Station
    • Utility Work in Progress at Dharavi
    • Barricade Board Shifting In Progress at Dharavi
    • Barricade Boards fixed at Santacruz Station
    • Excavation for utilities in progress between Grid 5 to Grid 10 at Vidyanagari Station
    • Piling Work in Progress at BKC Station
    • Utility Work in Progress at Dharavi
    • Dharvi Station Shifting of Utilities In progress along River side
    • Foundation Excavation in Progress for Project Site office at BKC Station
    • Pile Work in Progress at Vidyanagari Station
    • Trench work for Utilities in progress at Santacruz Station
    • Barricading at Vidyanagri station
    • Secant pile work at Vidyanagri North launching shaft
    • Site office at BKC Casting Yard
    • Site office work under progress at BKC station
    • Utility inspection at Santacruz
    • Utility shifting at Dharavi
    • Barricading work at BKC station
    • Dharavi Excavation for Utility Shifting
    • V idyanagri  station barrication in progress
    • Vidyanagri Sewer line excavation work
    • Barricading at Santacruz
    • Geo - Technical work at Vidyangari Station
    • Geo - Technical investigation at Dharavi
    • Reinforcement work at Vidyanagari Station
    • Utility identification at Dharavi
    • Barricading at Dharavi Station
    • Utility identification at Dharavi
    • Secant piling work at Vidyanagari station
    • Trial pit work for geo-technical investigation at BKC station
    • Geo - Technical investigation at Santacruz station
    83
    Package - 5
    15/07/2017
    • Grant Road -  MMRC's MD visit to Grant Road Site
    • CST - MMRC's MD visit to CST site Launching Shaft
    • Wadala - Segment Curing by Gunny Bags
    • Wadala - Aggregate Bin
    • CST - Muck Bin
    • CST - 1st Level Strut
    • CST - 1st Level Strut
    • CST - Preparatory work for Tree Transplantation
    • CST - Preparatory work for Tree Transplantation
    • CST - Transportation of Tree for Transplantation
    • Wadala - Master Ring Assembly
    • Wadala - Master Ring Assembly
    • CST - Waler beam for Rock Anchoring
    • CST - Gantry Crane Foundation
    • CST - Survey level checking for Anchoring
    • Grant Road - Piling Rig Calibration
    • CST - Inserting of Anchoring cable
    • CST - RCC breaking for Gantry Foundation
    • Wadala - Erection of Gantry Crane
    • CST - Level checking for tower crane foundation
    • CST - Muck Bin Excavation
    • Wadala - Erection of EOT track for Microfinishing Shed
    • Grant Road - Protection on either side of footpath for Public use
    • Wadala - Internal Road near Site office
    • Wadala - Safety Park near Entrance
    • CST - Instrumentation Monitoring near Launching Shaft
    • Wadala - Roofsheeting for Reinforcement Shed
    • Wadala - Roofsheeting for Reinforcement Shed
    • Wadala - Erection of Column for Microfinishaing Shed
    • CST - Bracing for king post upto 1st level excavation
    • Wadala - Electrification completed for Casting Yard
    • Wadala - Erection of CP30 Batching Plant Silos
    • Wadala - Erection of CP30 Batching Plant Silos
    • Wadala - Erection of CP30 Batching Plant Silos
    • Grant Road - Shifting of Utilities outside station box
    • Grant Road - Shifting of Utilities outside station box
    • Wadala - Boilers
    • Wadala - Erection of Rafter for Reinforcement Shed
    • Wadala - Foundation for Boiler
    • Wadala - Erection of Boiler
    • CST - Excavation at Launching Shaft
    • CST - Loading of Excavated Muck in dumper
    • CST - Fixing of brackets for installation of Waler
    • Wadala - Sedimentation Tank for M1 batching plant
    • Wadala - Aggregate Bin - 1st Wall Lift
    • Wadala - Erection of 2nd 10T Gantry crane inside casting shed completed
    • Wadala - Erection of Column & Surface dressing for Reinforcement Shed
    • Wadala - Segments inside Casting Shed
    • Grant Road - Plants & Shrubs Distribution stall at Pannalal Terrace
    • Grant Road - Plants & Shrubs Distribution at Pannalal Terrace
    • Grant Road - Plants & Shrubs Distribution at Pannalal Terrace
    • Grant Road - Plants and Shrubs distribution near Grant Road Station
    • CST - Client's Office preparatory Work
    • CST - Labour Rest Area
    • CST - Labour Rest Room - Dining Room
    • CST - Tool Box Talk by Station Manager
    • Wadala - Placing of Moulds inside casting shed
    • Wadala - Casting Shed
    • Wadala - Erection of Rafters
    • Wadala - Bracing for columns
    • Wadala - Joint Inspection of Moulds with GC
    • Wadala - Reinforcement tieing for casting bed
    • Wadala - Joint Inspection of Moulds with GC
    • Grant Road - Trenching for Utility Diversion
    • Grant Road - Barricading for Utility Trenching
    • Girgaon - Trial Trenching
    • Grant Road - Longitudinal Trenching work
    • CST - Safety speech by Construction Manager during Nation Safety Week
    • CST - Gathering for Nation Safety Week Flag Hosting
    • CST - Dismantling of old sheds around station box.
    • Wadala - Erection of Gantry Crane
    • Wadala - Erection of Gantry Crane
    • CST - Fabrication of King Post before lowering
    • Wadala - Erection of Columns for Casting Shed
    • CST - Worker's Rest Room Internal Partition work
    • CST Labour Rest Room
    • CST Secant Pile - Cage Lowering
    • WTC Labour Rest Room Plinth slab
    • Wadala Gantry Refurbishment for Casting bay
    • Wadala Casting Bay Foundation work in progress
    • Wadala Cleaning of Mould
    • Wadala Concrete breaking for Aggregate bin foundation and shed
    • Wadala Entry Gate at Wadala Casting Yard
    83
    Package - 2
    09/07/2017
    • MMRC Rehabilitation and Resettlement office in Kalbadevi
    • Mr. R. Ramana, Executive Director (Planning) inaugrating the Rehabilitation and Resettlement office in Kalbadevi
    • Mr. R. Ramana, Executive Director (Planning) being felicitated
    • Mr. R. Ramana, Executive Director (Planning) being felicitated
    • Team MMRC present for the occassion of inaugration of Rehabilitation and Resettlement office in Kalbadevi
    • Team MMRC present for the occassion of inaugration of Rehabilitation and Resettlement office in Kalbadevi
    6
    MMRC inaugurates Rehabilitation and Resettlement office in...
    10/05/2017
    • Mrs. Ashwini Bhide, MD, MMRC with Hon'ble CM, Shri Devendra Fadnavis during his visit to Metro - 3 alignment
    • Senior officials of MMRC including Mrs. Ashwini Bhide, MD, MMRC briefing Hon'ble CM, Shri Devendra Fadnavis on progress of Metro - 3
    • Senior officials of MMRC including Mrs. Ashwini Bhide, MD, MMRC briefing Hon'ble CM, Shri Devendra Fadnavis on progress of Metro - 3
    • Senior MMRC officials with Hon'ble CM, Shri Devendra Fadnavis
    • Senior MMRC officials with Hon'ble CM, Shri Devendra Fadnavis
    • Team MMRC along with Hon'ble CM, Shri Devendra Fadnavis
    6
    Honourable Chief Minister, Shri. Devendra Fadnavis paid...
    01/05/2017
Top