Photo Gallery

    • Nayanagar shaft piling work
    • Siddhivinayak Utility identification
    • SSV Utility identification
    • Geo-technical work at Shitladevi
    • Geo-technical work at Dadar
    • Footpath dismantling work at Dadar
    • Board painting work in progress
    • Barricades at Siddhivinayak
    • Nayanagar pile boring work
    • Nayanagar steel bending work
    • Nayanagar toilet work
    • Dadar area barricading for Geo - Technical work
    • Barricading at Shitladevi
    • Rig2 mobilized at Nayanagar
    • Siddhivinayak soil investigation
    • Siddhivinayak utility identification work
    • Naya nagar shaft guide wall
    • Naya nagar shaft pile boring
    • Naya nagar shaft pile concrete
    • Naya nagar shaft guide wall
    • Naya nagar shaft pile boring
    • Casting yard purlin erection casting yard
    • Casting yard
    • Casting yard column casting
    • SSV Utility identification Shitladevi
    • Barricade Board at Siddhivinayak
    • Dadar Barricading
    • Shitladevi Barricading
    • Barricading works at Dadar & shitladevi
    • Barricading works at Dadar & shitladevi
    • Meeting with senior Citizens at Siddhivinayak
    • Quality Checks at Batching plant
    • Rig Mobilized at Naya nagar
    • Casing driving at Naya nagar shaft
    • Nayanagar shaft Guide wall shuttering
    • Area barricading at Siddhivinayak station Sane Guruji Udyan
    • Gantry crane footing at wadala casting yard
    • Columb fabrication at Wadala casting yard
    • Soil investigation at SV-05 Siddhivinayak station
    • Soil investigation work is in progress siddhivinayak station
    • Soil investigation work is in progress Siddhivinayak station
    • Guide wall casting start at Naya nagar shaft
    • Excavation & PCC for gantry crane footing at Wadala casting yard
    • UG-4 contractor celebrated World AIDS Day at BKC and Naya nagar site
    • UG-4 contractor celebrated World AIDS Day at BKC and Naya nagar site
    • UG-4 contractor celebrated World AIDS Day at BKC and Naya nagar site
    • Soil investigation at Naya nagar
    • Sampling at Naya nagar during soil investigation
    • Soil investigation at BHT
    • Notification for tree cutting or transplantation
    • Barricading at BHT
    51
    Package - 4
    17/01/2017
    • Barricading at Dharavi Station
    • Geo-technical investigation at Santacruz
    • Secant piling work at Vidyanagari station
    • Trial pit work for geo-technical investigation at BKC station
    • Barricading at BKC station
    • Geo - Technical investigation at Santacruz station
    • Pile concreting work at Vidyanagari station
    • Secant pile work at Vidyanagari station
    • Secant pile work at Vidyanagari station
    • Utility investigation work at BKC station
    10
    Package - 5
    16/01/2017
    • MD & Director (Project), MMRC with team before the 6km Dream Run.
    • The contingent led by MD, MMRC
    • MD, MMRC leading the team during Dream Run.
    • MD, MMRC & Team keeping up the pace with other runners.
    • MD, MMRC & Team keeping up the pace with other runners.
    • Team MMRC creating awarness amongst people about Metro 3
    • MD, MMRC & Team successfully completes 6km Dream Run
    • MD, MMRC & Team in high spirits after completing the 6km Dream Run
    • MD, MMRC & Team post Dream Run
    9
    Dream Run of MMRC in Mumbai Marathon
    16/01/2017
    • Packer test at CSIA T2
    • Probe hole drilling at CSIA T2
    • Barricading at CSIA T2
    • Barricading at CSIA T2
    • Geotechnical Investigation works is in progress
    • Geotechnical Investigation at T1
    • Packers test in progress at CSIA T2
    • Reliance Electricity Utility at Sahar road
    • Demolition work of CSIA T1
    • Geotechnical Investigation at CSIA T1
    • Scrap extraction from CSIA T1
    • Steel extraction from Demolition work at CSIA T1
    • Site levelling at Barricading in progress at CSIA T2
    • Site preparation at CSIA T2
    • Utility investigation At Sahar road
    • Site-Prepration-for-Casting-Yard
    •  Secant-pile-boring-at-Sahar-road
    •  Pile-Cage-Reinforcement-binding-at-Sahar-Road
    • Geotechnical-investigation-at-CSIA-T2
    20
    Package - 6
    16/01/2017
    • Barricade fabraction at Casting yard
    • Geo-technical investigation at Mahalaxmi
    • Geo-technical investigation at Worli
    • Barricade fixing at Acharya Attre Chowk
    • Barricading at Science museum station
    • Barricade painting at Casting yard
    • Geo-technical rock sample at Mahalaxmi
    • Geo-technical rock sample at Worli
    • Mock drill at Science museum station
    • Reinforcement laying gantry crane foundation
    • Secant pile concreting at Science museum station
    • Utility diversion excavation at Science museum station
    • Utility investigation at Acharya Attre chowk
    • Barricade paintaing at Casting Yard
    • Barricading at Mahalaxmi
    • Barricading at Science Museum
    • Barricading at Worli engineering hub building MCGM
    • Foundation work at Casting Yard
    • Geo-technical investigation at Mahalaxmi
    • Geo-technical investigation at Worli
    • Reinforcement binding for foundation Casting Yard
    • Rock sample Acharya Attre Chowk
    • Secant pile frame setup at Science Museum
    • Structural steel painting ork at Casting Yard
    • Utility trenching at Mahalaxmi
    • Barricade Painting at Casting Yard
    • Geotechnical Investigation at Acharya Attre Chowk
    • Geotechnical investigation at Worli Station
    • Office layout marking at Casting Yard
    • PCC for gantry foundation
    • Utility Trenching at Science Museum
    • Bore Hole Samples
    • Fabrication of Barriacdes
    • Gantry crane foundation works
    • Geo-technical work
    • Piling rig callibaration at Science Museum
    • Geo-technical Investigation at Acharya Attre Chowk Station
    • Package - 3
    • Barricade Fabrication at Casting Yard Wadala
    • Trial trench excavation at Science Museum Station
    • Barricade fabrication
    • Utility trenching
    • Barricade Erection in progress at Science Museum Station
    • Area levelling in progress
    44
    Package - 3
    15/01/2017
    • Concreting for piles at Cuffe Parade
    • Erection of Batching Plant at pre-cast yard
    • Material for segment Casting shed
    • Utilities identification at Hutatma Chowk Station
    • Visit of CPM at Cuffe Parade
    • Erection of Batching Plant
    • Erection of Batching Plant
    • Erection of Batching Plant
    • Barricade at Vidhan Bhavan Station
    • Piling at Cuffe Parade
    • Inaugration of Safety Month
    • Area clearance at Launch Shaft Location
    • Barricade Fixing at CP Station
    • Barricade Fixing for Geo-technical Investigation at Hutatma Chowk
    • Batching Plant arrived at Casting Yard
    • Explaining Building Condition Survey to Residents
    • Trial Trench at CG Station
    • Barricade at Casting Yard
    • Foundation for Gantry Rails at Casting Yard
    • Shed Foundations at Casting Yard
    • SWM  Container Shifting
    • SWM  Container Shifting
    • Barrication Work
    • Geo - Technical investigation
    • Geo - Technical investigation
    • Barrication and Geo - Technical work at Vidhan Bhavan (27/11/2106)
    • Barrication painting work
    • Geo - Technical work at Vidhan Bhavan
    • Tree cutting notice
    • Trenching work at  Cuffe Parade
    30
    Package - 1
    15/01/2017
    • CST - Engineer's office External Wall sheet fixing work
    • CST - JV Office Roof erecting work
    • CST - Purlins erecting for Officer's mess roof
    • CST - Roof sheet erection for officer's mess
    • CST - Underground water tank for Worker's rest room
    • CST - JV office - PVC Panel fixing
    • CST - Secant Pile - Caseing Lowering for Pile P170
    • Wadala Casting Yard - Renovation of Existing Batching Plant
    • Wadala Casting Yard - Refurbishment of Weigh Bridge
    • Wadala Casting Yard - Reinforcement fixing for Gantry Track for Segment Stacking Bay - 2
    • Wadala Casting Yard - Reinforcement fixing for Gantry Track for Casting Bay
    • CST - Concreting for Secant Pile P84
    • CST - Contractor's Office erection of sheet for external wall & roof
    • CST - Contractor's Office  erection of sheet for external wall & roof
    • CST - Worker's rest room  erection of truss
    • CST - Engineer's Office fabrication of post for internal partition
    • Grant Road - Trail Trenching - Stage 1 - Exposed utilities
    • Grant Road - Trail Trenching - Stage 1 - Exposed utilities
    • CST - Installation of water tank for Press Club
    • Wadala - Casting Shed footing
    • Wadala - Reinforcement work for Gantry Track
    • Wadala - Weigh Bridge - Refurbishment work
    • Wadala - Renovated Bacthing Plant
    • CST - JV office Roof truss & Purlin erection completed
    • CST - JV Office - Sheet fixing for external wall in progress
    • Wadala - Curing by Gunny bags for footing of Castin bay shed
    • Wadala - Stub column curing by gunny bags
    • Grant Road - Trial Trenching - Stage 1
    • Grant Road - Trial Trenching - Stage 1
    • CST - Secant Pile S37 boring in progress
    • CST - Operating of wheel wash bay
    • CST - Safety note on inner face of barricading board
    • CST - Safety note on inner face of barricading board
    • Geotechnical Work at Girgaon - SDH-17
    • Geotechnical Investigation at Grant Road to Mumbai Central - TDH-7490
    • Barricading work at Grant Road - Work Area
    • CST - Secant pile and Polymer Tank set up
    • CST - JV Office plinth backfilling
    • Wadala Casting Yard - Safety walk with MMRC & Maple
    • Wadala Casting Yard - Casting bay excavation
    • Wadala Casting Yard - Concreting for barricading posts
    • CST - Demonstration on Fire fighting use of fire extinguisher
    • CST - 96 hours Training Room - Truss Shed fabrication
    • CST - Engineer`s Office - Preparation for compaction in backfilling
    • CST - JV Office - Vertical member erection in progress
    • CST - JV Office - Vertical Member Erection in progress
    • Casting Yard - Casting bay - Preparation for footing
    • Awareness program conducted on World AIDS Day
    • Public Information Center
    49
    Package - 2
    14/01/2017
    • 3.1m barrication works in progress at MIDC
    • Reliance substation shifting works in Progress at MIDC
    • Barrication on road at SEEPZ
    • Barrication on road at SEEPZ
    • Entry restricted at Marol Fire brigade area
    • Building demolition works at MIDC Police Quarters
    • Building demolition works at MIDC Police Quarters
    • Ground investigation works at CSIA
    • Street pole removal is in progress at Marol Naka
    • Piling works at Marol Launching Shaft
    • Baseline vibration monitoring started at National Test House SEEPZ Area
    • Concrete backfilling of trial trench-5 in progress at MIDC station
    • Micro piling works in progress at Project office, Pali ground
    • MIDC - police quarter - Reliance meter fixed
    • MIDC - Trial trench dewatering in progress & MTNL cable - 1 no, Tata Electric LT cable - 2 nos, Reliance Electric  LT cable - 2 nos. Utilities identified
    • Piling works In Progress Launching shaft
    • Trial trenching works in progress at Marol Naka Station
    • Wheel wash bay works In Progress at Launching shaft
    • Barrication boards painting in progress at MIDC station
    • Demolition-Works-In-Progress-at-MIDC-Station
    • Barrication-Board-Painting-In-Progress-at-MIDC-Station
    • Trial-Trenching-In-Progress-Marol-Naka-Station
    •  Barricading-Boards-Fixing-for-SI-Works-1
    • Barricading-Boards-Fixing-for-SI-Works
    • Baseline-Vibration-Monitoring-at-SEEPZ-multistory-building
    • Fencing-work-at-Pali-Ground-Site
    • Fencing-work-at-Seepz-station
    • Geotechnical-Investigation-work-in-progress-for-Tunnel-Alignment-Boreholes-at-Seepz
    • Geotechnical-Investigation-work-in-progress-for-Tunnel-Alignment-Boreholes-at-Seepz-1
    • Geotechnical-Investigation-work-is-in-progress
    • Installation-of-new-gate-at-Pali-Ground-Site
    •  Pile-Testing-at-Pali-Ground-Site
    • Pre-Start-Briefing-at-MIDC-station
    • Project-Office-Piling-work-started-at-Marol-Naka-Pali-Ground
    •  Trial-Trenching-is-in-Progress-at-Seepz-Station
    35
    Package - 7
    08/01/2017
    • Mrs. Ashwini Bhide presenting boquet to Dr. E. Sreedharan
    • Mrs. Ashwini Bhide presenting token of appreciation to Dr. E. Sreedharan
    • Mrs. Ashwini Bhide, MD MMRC with Dr. E. Sreedharan
    • Mrs. Ashwini Bhide, MD MMRC addressing at the occasion
    • Dr. E. Sreedharan addressing the Engineers of MMRC
    • Dr. E. Sreedharan interacting with the Engineers of MMRC
    • (From Left to Right) ; Mr. A. A. Bhatt, Director (Systems) MMRC, Mrs. Ashwini Bhide (MD) MMRC, Mr.R. Ramana, Executive Director (Planning) with Dr. E. Sreedharan
    • Senior Officials of MMRC, Engineers of MMRC and Genral Consultant at the interactive session
    • Dr. E Sreedharan guiding the Higher Official of MMRC and Civil Contractor
    9
    A talk by Dr. E. Sreedharan
    17/11/2016
Top