Photo Gallery

    • Tree distribution in Project Neighbourhood
    • Tree Neighbourhood program
    • Project Neighbourhood
    • Tree Plantation
    • Casting Yard Batching Plant setup
    • Casting Yard 1st Segment Demoulding
    • Casting Yard 1st Segment Demoulding
    • Nayanagar Piling Works
    • Nayanagar
    • Casting Yard National Safety Week
    • Casting Yard National Safety Day
    • Safety Week Casting Yard
    • Casting Yard  Binding
    • Dadar site container
    • Dadar Utility Identification
    • Gantry erection Casting Yard
    • Gantry erection Casting Yard
    • Pilling works Siddhivinayak
    • Barricading at Naya Nagar
    • Barricading at Siddhivinayak
    • Footpath excavation Road Widening at Dadar
    • Guide wall at Siddhi Vinayak
    • Guide wall at Siddhi Vinayak
    • Public Information Center
    • Castin Yard factory
    • Casting Yard Silos arrived
    • Guide wall preparatory Works at Siddhivinayak
    • Naya Nagar Shaft piling work is in progress
    • Worli to Siddhivinayak soil investigation work
    • Barricading at Siddhivinayak
    • Casting Yard
    • MGL Utilities at Siddhivinayak
    • Nayanagar Shaft piling work
    • Nayanagar shaft piling work
    • Nayanagar Shaft Piling work
    • Pilling works at Nayanagar
    • Profile sheet fixing at Casting Yard
    • Rock sampling during soil investigation
    • Shaft piling work at Nayanagar
    • Sidhivianayak Rig calibration
    • Soil investigation work
    • Siddhivinayak Utility identification
    • SSV Utility identification
    • Geo-technical work at Shitladevi
    • Geo-technical work at Dadar
    • Footpath dismantling work at Dadar
    • Board painting work in progress
    • Barricades at Siddhivinayak
    • Nayanagar pile boring work
    • Nayanagar steel bending work
    • Nayanagar toilet work
    • Dadar area barricading for Geo - Technical work
    • Barricading at Shitladevi
    • Rig2 mobilized at Nayanagar
    • Siddhivinayak soil investigation
    • Siddhivinayak utility identification work
    • Naya nagar shaft guide wall
    • Naya nagar shaft pile boring
    • Naya nagar shaft pile concrete
    • Naya nagar shaft guide wall
    • Naya nagar shaft pile boring
    • Casting yard purlin erection casting yard
    • Casting yard
    • Casting yard column casting
    • SSV Utility identification Shitladevi
    • Barricade Board at Siddhivinayak
    • Dadar Barricading
    • Shitladevi Barricading
    • Barricading works at Dadar & shitladevi
    • Barricading works at Dadar & shitladevi
    • Meeting with senior Citizens at Siddhivinayak
    • Quality Checks at Batching plant
    • Rig Mobilized at Naya nagar
    • Casing driving at Naya nagar shaft
    • Nayanagar shaft Guide wall shuttering
    • Area barricading at Siddhivinayak station Sane Guruji Udyan
    • Gantry crane footing at wadala casting yard
    • Columb fabrication at Wadala casting yard
    • Soil investigation at SV-05 Siddhivinayak station
    • Soil investigation work is in progress siddhivinayak station
    • Soil investigation work is in progress Siddhivinayak station
    • Guide wall casting start at Naya nagar shaft
    • Excavation & PCC for gantry crane footing at Wadala casting yard
    • UG-4 contractor celebrated World AIDS Day at BKC and Naya nagar site
    • UG-4 contractor celebrated World AIDS Day at BKC and Naya nagar site
    • UG-4 contractor celebrated World AIDS Day at BKC and Naya nagar site
    • Soil investigation at Naya nagar
    • Sampling at Naya nagar during soil investigation
    • Soil investigation at BHT
    • Notification for tree cutting or transplantation
    • Barricading at BHT
    92
    Package - 4
    20/03/2017
    • Bore Hole Work in Progress at Sanatacruz Station
    • Excavation work for Utility in progress at Vidyanagari Station
    • Foundation Footing RCC done at BKC Station
    • Utility Work in Progress at Dharavi
    • Barricade Board Shifting In Progress at Dharavi
    • Barricade Boards fixed at Santacruz Station
    • Excavation for utilities in progress between Grid 5 to Grid 10 at Vidyanagari Station
    • Piling Work in Progress at BKC Station
    • Utility Work in Progress at Dharavi
    • Dharvi Station Shifting of Utilities In progress along River side
    • Foundation Excavation in Progress for Project Site office at BKC Station
    • Pile Work in Progress at Vidyanagari Station
    • Trench work for Utilities in progress at Santacruz Station
    • Barricading at Vidyanagri station
    • Secant pile work at Vidyanagri North launching shaft
    • Site office at BKC Casting Yard
    • Site office work under progress at BKC station
    • Utility inspection at Santacruz
    • Utility shifting at Dharavi
    • Barricading work at BKC station
    • Dharavi Excavation for Utility Shifting
    • V idyanagri  station barrication in progress
    • Vidyanagri Sewer line excavation work
    • Barricading at Santacruz
    • Geo - Technical work at Vidyangari Station
    • Geo - Technical investigation at Dharavi
    • Reinforcement work at Vidyanagari Station
    • Utility identification at Dharavi
    • Barricading at Dharavi Station
    • Utility identification at Dharavi
    • Geo-technical investigation at Santacruz
    • Secant piling work at Vidyanagari station
    • Trial pit work for geo-technical investigation at BKC station
    • Barricading at BKC station
    • Geo - Technical investigation at Santacruz station
    • Pile concreting work at Vidyanagari station
    • Secant pile work at Vidyanagari station
    • Secant pile work at Vidyanagari station
    • Utility investigation work at BKC station
    • Barricading work at Santacruz station
    • Geo-technical investigation at Dharavi station
    • Geo-technical investigation at Dharavi station
    • Piling work at Vidyanagri station
    • Temporary office setup at BKC station
    • Utility Investigation at Santacruz station
    45
    Package - 5
    20/03/2017
    • Column erection for casting yard shed at Casting Yard
    • Secant piling at Science Museum
    • Utility investigation at Mumbai Central
    • Utility investigation at Mahalaxmi
    • Utility investigation at Acharya Attre
    • Aerail view of Mumbai Central
    • Barricade placing at Worli
    • Borehole investigation at Worli
    • Borehole sample Worli
    • Rock sample at Acharya Attre
    • Site office establishment at Casting Yard
    • Site office establishment Construction Depot
    • Casting Yard Column Erection
    • Column erection Casting Yard
    • Geotechnical Investigation Mumbai Central
    • Office setup Construction Depot
    • Pollution monitoring meter Casting Yard
    • Secant piling Science Museum
    • Site office establishment
    • Site office setup Construction Depot
    • Utility diversion work Science Museum
    • Utility trenching Science Museum
    • Utility trenching Mahalaxmi
    • Utility trenching Worli
    • Barricade painting Casting Yard
    • Barricade fixing Worli
    • Borehole sample Mumbai Central
    • Gantry crane foundation Casting Yard
    • Barricade fixing science museum
    • Secant Piling Science Museum
    • Site office establishment Casting Yard
    • Utility investigation Acharya Attre
    • Barricade fixing at Acharya Attre
    • Barricade fixing at Mahalaxmi
    • Barricade fikxing at Worli
    • Barricading at Naya Nagar
    • Foundation works office at Casting Yard
    • Geo - Technikcal investigation at Mumbai Central
    • Secant piling at Science Museum
    • Site office depot construction work
    • Utility investigation at Acharya Attre
    • Utility trenching at Worli
    • Aerial view Mumbai Central
    • Barricading at Mumbai Central
    • Bore Hole sampl at Worli
    • Concreting of segment casting area shed at Casting Yard
    • Excavation for utility diversion works at Science Museum
    • Gantry crane foundation works at Casting Yard
    • Secant piling at Science Museum
    • Site office estalishment at Casting Yard
    • Utility investigation at Acharya Attre
    • Barricade fixing Science Museum
    • Geo-technical investigation at Worli
    • Secant piling Science Museum
    • Utility diversion work Science Museum
    • Utility investigation Acharya Attre Chowk
    • Utility investigation Science Museum
    •  Borehole samples mahalaxmi
    • Borehole samples worli
    •  Excavation for utiility diversion science museum
    • Gantry crane foundation casting yard
    • Geotechnical investigation mahalaxmi
    • Geotechnical investigation worli
    • Office buikding foundation works casting yard
    • Office buikding foundation works casting yard
    • Office building foundation works construction depot
    •  Utility investigation acharya attre
    • utility trenching science museum
    68
    Package - 3
    19/03/2017
    • Piling Rig at Vidhan Bhavan station
    • Segment Moulds at pre-cast yard
    • Watering of ne trees planted at Aarey Colony
    • Breifing to Workmen
    • Isolating public from Trial Trenches to ensure safety
    • Method statement breifing to Site Engineers
    • Prepardness in case of Fire Emergency
    • Safe storage of materials
    • Seggregating Scrap Materials
    • Tool box talk by Station Manager before start of work
    • View of Casing Yard from Freeway
    • Waste Seggregation at Work Areas
    • Area preparation at Aarey Colony for tree plantation
    • Area preparation for plantation of new trees at Aarey Colony
    • New saplings for plantation at Aarey Colony
    • Chief Resident Engineer planting new tree at Aarey Colony
    • New tree planted at Police Gymkhana
    • Erection of Gantry at Casting Yard
    • Erection of Gantry at Casting Yard
    • High fencing near residential buildings
    • Commencement of Piling at Vidhan Bhavan Station by Chief Resident Engineer (MAPLE)
    • MMRC Managing Director at Vidhan Bhavan Site Office
    • Feeding Cement into Hopper at Batching Plant in Casting Yard
    • Erection of Hopper at Batching Plant in Casting Yard
    • Traffic Barrication as per Guidelines
    • Taining to workmen on good construction practices
    • Area preparation at MIDC land near Backbay Bus Depot
    • Completed piles at Cuffe Parade Station
    • Creating work front to commence piling at Vidhan Bhavan Station
    • Exclusive fencing to protect Colaba Woods Garden
    • Preparation for National Safety Day
    • Flag Hoisting during National Safety Day
    • Safety pledge during National Safety Day celebration
    • Gantry erection at Casting Yard
    • Pile boring at Cuffe Parade Station
    • Piling at TBM Launch Shaft location
    • Securing work areas
    • Laying of track for Gantry at Casting Yard
    • Use of safe loading, unloading and transportation methods for heavy materials
    • Distribution and watering of plants at societies in vicinity of Work Areas
    • Watering work area at regular intervals for dust control
    • Excavation for Utility Diversion
    • Assembling EOT crane for erection at Casting Yard
    • Construction of Segment Casting Shed
    • Achieving perfection by using guidewall for secant pile
    • Dust control by regular watering at Work Areas
    • Ensuring safety to commuters
    • Prepardness for Traffic diversion
    • Protection of trees at work area
    • Quality lab next to batching plant at Casting Yard
    • Round the clock work to meet deadlines
    • Saplings to plant around work areas and site offices
    • Area preparation for piling at Vidhan Bhavan
    • Area development at MIDC depot land
    • Barricade at DN Road
    • Barricades and sikgnboards at locations of building demolition
    • Contractor's project office under construction
    • Isolating traffick from wolrk area near Vidhan Bhavan
    • Piling at launch shaft location at Cuffe Parade
    • Providing safe access to residents at vicinity of MIDC area
    • Provoding safe pedestrian path near Vidhan Bhavan
    • Providing directions for safety of pedestrians
    • Rest area for workmen at wolrksite
    • Safety toolbox talk to workmen before start of work
    • Separating public from work area for Utility identification work
    • Preparaton for commencement of piling work at Cuffe Parade
    • Demolition activities at Vidhan Bhavan
    • Emergency display at utility diversion locations
    • Geo-technical investigation for tunnel between Vidhan Bhavan and Churchgate
    • Comencement of piling at Launching Shaft
    • Trial trench at Vidhan Bhavan
    • Truss erection pre-cast shed
    • Barricading at Vidhan Bhavan
    • Barricading at Hutatma Chowk
    • Demolitian at Vidhan Bhavan station
    • Fencing in progress at MIDC
    • Geo-technical investigation for tunnel at Vidhan Bhavan
    • Piling cage lowering at Cuffe Parade
    • Trial trench at Cuffe Parade
    • Tree cutting at Cuffe Parade
    • Tree cutting at Vidhan Bhavan
    • Trial trench for utility identification at Vidhan Bhavan
    • Shed truss rescting at casting yard
    • Plinth preparation for Project office at oval maidan
    • Tree sutting at cuffe Parade
    • Traffic management at DN Road
    • Utilities iduentified at Vidhan Bhavan
    • Survey at prposed land for tree
    • Shed Erection at casting yard
    89
    Package - 1
    19/03/2017
    • Batching Plant Foundation at Casting Yard
    • Factory Shed Foundation at Casting Yard
    • Gantry Foundation-03 at Casting Yard
    • Gantry Foundation-004 at Casting Yard
    • Labour Rest room and Canteen at  CSIA international station
    • Labour toilets making in progress at CSIA international station
    • Piling Work in progress at internatioanl Station
    • Probe hole-11 in Progress at International station
    • Secant Pile Marking in progress at CSIA DOmestic Airport
    • Stacking Area-04 at Casting Yard
    • Weigh Bridge at Casting Yard
    • BHT-12 Backfilling and Concrete of Bore hole for tunnels
    • Guide frame fabrication for piling work
    • Cube curing tank at international station
    • Construction of road at Casting yard
    • Gantry Foundation work at Casting yard
    • Electric room construction work at International station
    • New Segment moulds reached at Casting yard
    • Pile concreting at Sahar road station
    • Piling started by new piling rig at Sahar road station
    • Probe hole No. -07 in progress at international station
    • Reinforcemet work for batching plant foundation at Casting Yard
    • Steel yard at International station
    • Trenching for 1800 mm water line at CSIA Domestic Airport
    • Waste water tank construction under progress at International station
    • Water sprinkling at Sahar road station for dust supression
    • Barricade fixing at Hutatma area at Sahar road station
    • BHT -10 (For Tunnels) trenching work
    • Cage lowering for hard pile at Sahar Road Station
    • Cage lowering for hard pile at Sahar Road Station1
    • Fixing of Station box alignment at International Station
    • Geotechnical investigation at BHT-09 (For Tunnels) in Progress
    • Geotechnical investigation at BHT-16 (For Tunnels) in Progress
    • Guide frame  fabrication work in progress for piling at Internatinal station
    • Hard pile bore, Cut in soft pile at Sahar road station
    • Labour Canteen and Rest room Work in progress at International Station1
    • NATM-01 Machine Installation work for geotechnical investigation in progress at CSIA T1 Domestic station
    • PCC for barricade fixing Hutment area at Sahar road station
    • PCC for steel yard at CSIA T2 (International  station)
    • Pile concreting at Sahar Road Station
    • Piling rig is under caliberation at CSIA T2 international station
    • Probe hole Drilling at CSIA T2 International Station
    • BHT-16(For Tunnels) Rock sample
    • Waste water tank construction at CSIA T2 international station
    • Cage reinforcement for Secant Pile at Sahar road station
    • Gantry Foundation PCC at casting yard
    • Gantry Line-4 Reinforcement at Casting yard
    • Gantry foundation Reinforcement at Casting yard
    • Entry-Exit gate at CSIA T2 (international station)
    • Cement Gowdown construction at construction depot
    • Geotechnical Investigation at BHT-12 (For Tunnels)
    • Geotechnical Investigation at BHT-16 (For Tunnels)
    • Geotechnical Investigation Samples at BHT-12 (For Tunnels)
    • Labour rest room Fabrication work at CSIA T2 International Station
    • Labours rest room  Fabrication Work at CSIA T1 (Domestic Airport Station)
    • Probe hole Drilling PH-01 at CSIA T1 (Domestic Station)
    • Probe hole drilling at CSIA T2 (internatinal station)
    • RMC Plant at Construction Depot
    • Tool Box talk at Sahar station
    • Wheel wash Bay at sahar road station
    • Geotechnical Investigation at CSIA Domestic Station
    • Geotechnical Investigation at Domestic Station
    • Probe Hole work in progress at CSIA International station
    • Public information center at Sahar road station
    • Scrap steel cutting and segregation work in progress
    • Site Office establishment at International station
    • Soft pile concreting at Sahar Road Station
    • Septic tank at Construction Depot
    • Store Room fabrication at Domestic Station
    • Wheel wash bay at Sahar Road Station
    • Site office at Sahar Road
    • Tool changing in progress at Sahar Road
    • Secant Piling in progress
    • Packer test at CSIA T2
    • Probe hole drilling at CSIA T2
    • Barricading at CSIA T2
    • Barricading at CSIA T2
    • Geotechnical Investigation works is in progress
    • Geotechnical Investigation at T1
    • Packers test in progress at CSIA T2
    • Reliance Electricity Utility at Sahar road
    • Demolition work of CSIA T1
    • Geotechnical Investigation at CSIA T1
    • Scrap extraction from CSIA T1
    • Steel extraction from Demolition work at CSIA T1
    • Site levelling at Barricading in progress at CSIA T2
    • Site preparation at CSIA T2
    • Utility investigation At Sahar road
    • Site-Prepration-for-Casting-Yard
    •  Secant-pile-boring-at-Sahar-road
    •  Pile-Cage-Reinforcement-binding-at-Sahar-Road
    • Geotechnical-investigation-at-CSIA-T2
    93
    Package - 6
    18/03/2017
    • Wadala - Erection of Rafters
    • Wadala - Bracing for columns
    • Wadala - Joint Inspection of Moulds with GC
    • Wadala - Reinforcement tieing for casting bed
    • Wadala - Joint Inspection of Moulds with GC
    • Grant Road - Trenching for Utility Diversion
    • Grant Road - Barricading for Utility Trenching
    • Girgaon - Trial Trenching
    • Grant Road - Longitudinal Trenching work
    • CST - Safety speech by Construction Manager during Nation Safety Week
    • CST - Gathering for Nation Safety Week Flag Hosting
    • CST - Dismantling of old sheds around station box.
    • Wadala - Erection of Gantry Crane
    • Wadala - Erection of Gantry Crane
    • CST - Fabrication of King Post before lowering
    • Wadala - Erection of Columns for Casting Shed
    • CST - Worker's Rest Room Internal Partition work
    • CST Labour Rest Room
    • CST Secant Pile - Cage Lowering
    • WTC Labour Rest Room Plinth slab
    • Wadala Gantry Refurbishment for Casting bay
    • Wadala Casting Bay Foundation work in progress
    • Wadala Cleaning of Mould
    • Wadala Concrete breaking for Aggregate bin foundation and shed
    • Wadala Entry Gate at Wadala Casting Yard
    • WTC Rubble Soling for Approach slab of Weigh Bridge
    • WTC Reinforcement stacking yard
    • CST Rubble soling for Substation Foundation
    • CST Secant Pile near retrieval shaft area
    • CST Secant Pile near Launching Shaft
    • CST King Post by DTH Boring Machine
    • Wadala PCC in Casting Shed Flooring
    • Wadala Reinforcement fixing work in Casting Shed
    • Wadala Foundation work for CP30 batching plant
    • WadalavFoundation for Rebar Shed
    • Wadala Factory Shed Gantry Track
    • CST JV Office Fixing of pannels for ceiling
    • CST Boring for secant pile
    • WTC Brickwork for reinforcement scrap yard
    • CST JV Office  Vinyl flooring work
    • CST Erection of structual steel for Overhead water tank & Excavation for Underground water tank
    • CST Installation of Cage for secant pile
    • CST Secant Pile work
    • CST Sheet fixing for Labour rest room
    • WTC Stub column for labour rest room
    • Wadala casting Yard Concreting for Factory shed Gantry Track Raft
    • Wadala Casting Yard PCC for Stacking Yard 1
    • Wdala Casting Yard Shuttering for Factory Shed Tie Beam
    • Wadala Casting Yard Segement Stacking bay 2
    • CST JV Office Flooring in progress
    • CST Toilet for Workers Rest
    • CST Workers Rest Room Angle fixing for External sheet fixing
    • Grant Road - Barricading for Longitudinal Trenching
    53
    Package - 2
    18/03/2017
    • Chipping work of piles for Capping beam in Progress at Mid Shaft area
    • Barricading cleaning work in progress at Seepz Station
    • Curing after concrete work for SWD (2m x 2m) diversion in progress at Seepz Station
    • Office construction - Ground Floor & First Floor Finishing work in Progress at Pali Ground
    • Primary Pile P-39 in Progress at Mid Shaft area (Pali Ground)
    • Primary Pile P-41 drilling in Progress at Mid Shaft area (Pali Ground)
    • Raft Reinforcement work in progress for SWD Drain (2mtr x 2mtr) inside the Seepz
    • Rebar Cutting & bending work in progress for SWD at Seepz Station
    • Retaining wall raft construction in MIDC
    • Safety Tool Box Meeting at Seepz Station
    • Signage fixing work in progress at Seepz Station
    • Secant Piling works in Marol Naka
    • Store Foundation work in Progress at Mid Shaft area
    • Wall shuttering work for Storm Water Drain (2m x 2m) diversion at Seepz Station
    • Worker rest room for Seepz Station
    • Waterline Diversion Works in Marol Naka
    • Casting yard works in progress
    • Casting yard works in progress
    • Project office false ceiling works in progress
    • Project office flooring works in progress
    • Retaining structure excavation is in progress at MIDC
    • Secant piling works in progress at Marol Naka
    • Segment mould received at Casting Yard
    • Segment mould at Casting Yard
    • Waterline diversion works in progress at Marol Naka
    • DTH pilling work for P-38 in Progress at Mid Shaft area
    • First Floor Truss erection & Ground Floor False Ceiling in Progress at Mid Shaft area (Pali Ground)
    • Further Excavation for Storm Water Drain (2m x 2m) diversion in progress at Seepz
    • Gantry erection work in progress at Casting Yard
    • Gantry erection work in progress at Casting Yard  1
    • Secant Piling works at Marol Naka
    • Office construction work
    • Retaining structure excavation is in progress at MIDC
    • Secant pile chipping work for capping beam in Progress at Mid Shaft area (Pali Ground)
    • Safety Talk for bar bending, shuttering & housekeeping at Seepz Station
    • Water sprinkling for dust control in progress at Seepz Station
    • Column footing work for Casting Shed in progress at Casting Yard
    • Column footing work for Casting Shed in progress at Casting Yard
    • Column footing work for Casting Shed in progress at Casting Yard
    • Column footing work for Casting Shed in progress at Casting Yard
    • Column footing work for Casting Shed in progress at Casting Yard
    • Office Construction work is in progress
    • Secant pile S-23 piling work in progress at Mid Shaft area
    • Secant pile S-32 cage lowering work in progress at Mid Shaft area
    • Store Foundation in Progress Mid Shaft area (Pali Ground)
    • Tool box safety meeting held on every day at Seepz Station
    • Secant Pile Chipping work start from 23/02/2017 at Mid Shaft area (Pali Ground)
    • Retaining structure construction is in progress at MIDC
    • Storm water drain diversion (Raft concrete) work in progress at Seepz Station
    • Storm water drain diversion (Raft concrete) work in progress at Seepz Station
    • Excavation work for Gantry foundation in progress at Casting Yard
    • Compaction work for Gantry foundation in progress at Casting Yard
    • PCC work for Gantry foundation in progress at Casting Yard
    • Storm water drain diversion (Reinforcement) work in progress at Seepz Station
    • Storm water drain invert level marking work in progress at Seepz Station
    • Storm water drain manual excavation in progress at Seepz Station
    • Storm water drain PCC work at Seepz Station
    • Muck removal work in progress at Seepz Station
    • Housekeeping work at Seepz Station
    • New foundation for shifting of existing Reliance transformer Gantry foundation in progress at Casting Yard
    • Project office construction work is in progress
    • Piling rig mobilized at Marol Naka station
    • Piling work is in progress at Mid Shaft
    • Piling work is in progress at Mid Shaft
    • Reliance Substation shifting work is in progress at MIDC station
    • Retaining wall excavation work is in progress at MIDC station
    • Secant Secondary pile work in progress at Mid Shaft area (Pali Ground)
    • Site Office construction work - Ground floor erection completed & 1st floor erection work in progress at Mid Shaft area (Pali Ground)
    • Store foundation work started at Mid Shaft area (Pali Ground)
    • SWD diversion work is in progress at Marol Naka station
    • Wheel wash bay construction work is in progress at Marol Naka station
    • Debris removal work is in progress at MIDC station
    • Barricading at Seepz
    • Board Installation work is in progress for Main Gate Casting Yard
    • CCTV Camera Installation work completed outside the Seepz
    • ESIC Firefighting Line Shifting work is in progress at MIDC Station
    • ESIC Firefighting Line Shifting work is in progress at MIDC Station
    • ESIC Firefighting Line Shifting work is in progress at MIDC Station
    • ESIC Firefighting Line Shifting work is in progress at MIDC Station
    • PCC Flooring Completed & GF Bracing Fixing work in progress 99/329 Erected at Mid Shaft area (Pali Ground)
    • PCC Flooring Completed & GF Bracing Fixing work in progress 99/329 Erected at Mid Shaft area (Pali Ground)
    • PCC Flooring Completed & GF Bracing Fixing work in progress 99/329 Erected at Mid Shaft area (Pali Ground)
    • PCC Flooring Completed & GF Bracing Fixing work in progress 99/329 Erected at Mid Shaft area (Pali Ground)
    • Utility identification work before starting of Bore Hole at Seepz Station
    • Casting Yard
    • Casting Yard
    • Mid Shaft at Pali ground
    • Mid Shaft at Pali ground
    • Mid Shaft at Pali ground
    • Street light pole dismantling work is in progress at Seepz Station
    • Excavation Started for Storm water Drain Diversion at Seepz Station
    • CCTV Pole Dismantling work is in Progress at Seepz Station
    • Taxi Stand Dismantling work in progress at Seepz Station
    • Secant Pile (P62 & S12) work is in Progress at Pali Ground
    • Drain work is in progress at Pali Ground
    • Site Office Plinth Beam work is in progress at Pali Ground
    • Casting shed footing work in progress at Casting Yard
    • SWD diversion work in progress at Marol Naka
    • Reliance Substation shifting work in progress at MIDC ESIC area
    • 4m barrication work in progress at Marol Naka
    • Debri removal work in progress at MIDC Police Quarters
    101
    Package - 7
    19/02/2017
    • MD & Director (Project), MMRC with team before the 6km Dream Run.
    • The contingent led by MD, MMRC
    • MD, MMRC leading the team during Dream Run.
    • MD, MMRC & Team keeping up the pace with other runners.
    • MD, MMRC & Team keeping up the pace with other runners.
    • Team MMRC creating awarness amongst people about Metro 3
    • MD, MMRC & Team successfully completes 6km Dream Run
    • MD, MMRC & Team in high spirits after completing the 6km Dream Run
    • MD, MMRC & Team post Dream Run
    9
    Dream Run of MMRC in Mumbai Marathon
    16/01/2017
    • Mrs. Ashwini Bhide presenting boquet to Dr. E. Sreedharan
    • Mrs. Ashwini Bhide presenting token of appreciation to Dr. E. Sreedharan
    • Mrs. Ashwini Bhide, MD MMRC with Dr. E. Sreedharan
    • Mrs. Ashwini Bhide, MD MMRC addressing at the occasion
    • Dr. E. Sreedharan addressing the Engineers of MMRC
    • Dr. E. Sreedharan interacting with the Engineers of MMRC
    • (From Left to Right) ; Mr. A. A. Bhatt, Director (Systems) MMRC, Mrs. Ashwini Bhide (MD) MMRC, Mr.R. Ramana, Executive Director (Planning) with Dr. E. Sreedharan
    • Senior Officials of MMRC, Engineers of MMRC and Genral Consultant at the interactive session
    • Dr. E Sreedharan guiding the Higher Official of MMRC and Civil Contractor
    9
    A talk by Dr. E. Sreedharan
    17/11/2016
Top