छायाचित्र दालन (Photo Gallery)

    • Vidyanagari Excavations
    • BKC Station Excavations
    • Santacruz Station Excavations
    • Dharavi Station Cable Diversion
    • Dharavi Station Anchoring Gr (15-17)
    • BKC Station Excavation
    • Vidyanagari Base Slab Work
    • Vidyanagari Excavation
    • BKC Station
    • BKC Station South Shaft
    • Santacruz Excavation
    • Bandra Station Excavation Gr - 01 - 14
    • Bandra Station Excavation Gr - 19 - 35
    • Santacruz Gantry Erection
    • Vidya Nagri Station Excavation Station Box
    • Vidya Nagri Station Shotcrete South Shaft
    • Dharavi Station Cable Diversion
    • Bandra Station Excavation
    • Santacruz Station - Excavation
    • Santacruz Station - Micro Piling
    • Vidyanagari Station - Excavation
    • Vidyanagari Station TBM Muck pit
    • Bandra Station ITO junction piling
    • Bandra Station North Shaft base slab
    • Dharavi Station - Canti lever slab casting
    • Dharavi Station - Kingpost east wall
    • Santacruz Station - Consolidated grouting
    • Bandra Station-Traffic diversion (G19-25)
    • Dharavi Station-King post
    • Bandra Station-South shaft
    • Dharavi Station-Secant piling(Ancillary)
    • Vidyanagari Station 600mm Pipe line
    • Bandra Station Road construction - Junction
    • Dharavi Station Road construction North junction
    • Dharavi Station Road construction South junction
    • Vidyanagari Station Struts
    • Santacruz Station Traffic Diversion (South End)
    • PCC Casting
    • 600mm Pipeline Diversion - East wall
    • East wall -1200mm Pipeline
    • Flood wall construction - West wall
    • PCC Casting - Launching shaft
    • T61 - Mucking
    • Bandra Station north shaft
    • Dharavi station gabion wall
    • Dharavi station piling east wall
    • New Police Station - Santacruz Station
    • North Shaft
    • North Shaft - Vidyanagari Station
    • TBM lowering has commenced at Vidyanagri North Launching shaft
    • TBM lowering has commenced at Vidyanagri North Launching shaft
    • TBM lowering has commenced at Vidyanagri North Launching shaft
    • SWD Pipe laying(Santacruz)
    • Caping beam(BKC)
    • Secant Piling at Station Box
    • Capping Beam (Dharavi)
    • Piling (BKC)
    • Launching Shaft (Vidyanagari)
    • Gabion Wall(Dharavi)
    • Excavation of Launching Shaft Ongoing at Vidyanagari Station
    • Labour Camp Erection ongoing at Vidyanagari Station
    • Piling Work ongoing at Santacruz Station
    • Piling Work ongoing at Dharavi Station
    • Mangrooves Area Cleaning on going at BKC Station
    • BKC - Piling, Backfilling
    • BKC Project Office - Flooring Works
    • Santacruz-Micro Piling
    • Vidyanagri - Road for Traffic Diversion
    • Vidyanagri North Shaft - Excavation 1
    • Vidyanagri North Shaft - Excavation 2
    • Santacruz-Secant Piling
    • Dharavi - Secant Piling
    • Dharavi - Reinforcement fixing for Capping Beam
    • BKC Station Grid
    • Excavation work ongoing at Vidyanagari Station
    • Piling work ongoing at Dharavi Station
    • Piling Work ongoing at Santacruz Station
    • BKC - North Launching Shaft
    • BKC Steel Yard - Batching Plant Erection Ongoing
    • BKC - Project Office
    • Vidyanagri - Piling (Gr 1 to 6 - West)
    • Dharavi - Pile Chipping for Capping Beam (Gr 1 to 6 - Nallah Side)
    • Dharavi - 2nd Piling Rig Mobilised
    • Vidya Nagari North Shaft - Pile Chipping for Capping Beam Preparation
    84
    Package - 5
    09/12/2018
    • Girgaon Station Demolition wroks
    • Grant Road Station - Sewerline diversion works
    • Grant Road Station - Sewerline diversion works
    • Grant Road Station - Excavation and Strutting
    • SCA - Pour - 04
    • Girgaon Building Demolition
    • SCS - Rebar binding or tying work for main wall Down line side
    • SCS - GC 7 column shuttering working in progress
    • Grant Road Station  - Phase 3 excavation works
    • SCS-Excavation for diversion of 600mm and 450mm water main is in progress with 4 labours opposite to Cama Hospital EE2
    •  Grant Road Station- Excavation at Phase 03 for decking
    • Grant Road Station- Barricade maintenance
    • CST- 3rd pour completed for station
    •  Base Slab Pour 3 - CST Station
    •  Capping Beam Grant Road Station
    •  Excavation Work Near Pannalal Terrace for Decking
    • Batching plant
    • Capping beam - Grant Road Station
    • Road Breaking - Grant Road Station
    • Road Rectification
    • Secant Pile - Grant Road Station
    • Soldier Pile - Grant Road Station
    • Traffic Diversion - Girgaon Station
    • Base Slab 3rd pour - PCC - CST
    • Pedestrain Walkway - Grant Road Station
    • Rock Breaking - CST
    • Secant Pile - Grant Road Station
    • Traffic Diversion - GRant Road Station
    • Tunnel Work
    • Tunnel Work
    • Utility Diversion - Girgaon Station
    • Traffic Diversion - Grant Road Station
    • Secant Pile - Grant Road
    • Earth Mat Laing - CST
    •  Column Pedestal - CST
    • Building Demolition - Girgaon Station
    • Road Diversion - Girgaon
    • Road Diversion - Grant Road
    • Secant Pile Phase -5 - Grant Road
    • Utility Diversion - Girgaon
    • Utility Diversion - CST
    • Girgaon station secant pile works
    • Girgaon station demolition works
    • Grant Road  station secant pile works
    • Grant Road  station secant pile works
    • Grant Road  station secant pile works at bank side
    • Girgaon - Phase 1, 2 & 6
    • Girgaon - Phase - 9
    • Grant Road - Phase - 1&4-1
    • Girgaon - Phase - 11 - Junction.
    • Grant Road - Phase - 1&4
    • CST - Rock Breaking in Station Box
    • CST - Rock Breaking in Station Box
    • Grant Road - Erection of Extra support for Raja Terrace
    • Grant Road - King Post area breaking for Erection of Built up section
    • Girgaon - Construction of Retaining Wall
    • Grant Road - Secant Piling in Phase 6
    • Grant Road - Secant Pile breaking in Phase 3
    • Grant Road - Secant Piling in Phase 4
    • CST - Station Box Excavation
    • Girgaon - Phase 2 & 3
    • Girgaon - Piling at Phase 9
    • Tunnel 1 - Boring by Vaitana-1
    • Tunnel 1 - Denotation of Tunnel Utilities
    • CST - Station Box
    • CST - Retrieval Shaft Strut Erection
    • CST - Excavation in Station Box
    • Girgaon - Retaining Wall and Utility Diversion in Phase 9
    • Girgaon - MTNL Telephone line diversion
    • CST - Launching-Shaft - Operation of Locomotive begins
    • CST - Launching-Shaft - Lowering of Locomotive
    • CST - Tunneling Ring Building
    72
    Package - 2
    09/12/2018
    • Marol Naka
    • Marol Naka
    • MIDC
    • SEEPZ
    • MIDC
    • Marol Naka
    • Marol Naka
    • MIDC
    • Marol Naka
    • MIDC
    • Ramp Shaft
    • SEEPZ
    • Marol Naka
    • Marol Naka
    • SEEPZ
    • MIDC
    • MIDC
    • Marol Naka
    • MIDC
    • SEEPZ
    • SEEPZ
    • Marol Naka box - A
    • Marol Naka box - B
    • MIDC
    • SEEPZ
    • Marol Naka Box - A
    • Marol Naka
    • Marol Naka
    • Marol Naka
    • Marol Naka
    • SEEPZ
    • MIDC
    • MIDC
    • Marol Naka
    • MIDC
    • MIDC
    • Casting Yard
    • Marol Naka
    • Marol Naka
    • MIDC
    • Mid Shaft
    • Ramp
    • Seepz
    • MIDC
    • MIDC
    • MIDC
    • MIDC
    • MIDC
    • Ramp
    • SEEPZ
    • TBM Assembling
    • SEEPZ
    • Tunneling in progress - Wainganga
    • Casting Yard - Training Mould Cleaning
    • Decking work in progress at SEEPZ Station
    • Marol Naka
    • Marol Naka
    • MIDC
    • SEEPZ
    • Tunnel
    • Tunnel
    • VAINGANGA - 1 Assembling at Mid-Shaft
    • VAINGANGA - 1 Parts lowering at Mid-Shaft
    • Excavation works at Marol Naka Station
    • Excavation works at Marol Naka Station
    • Excavation works at MIDC Station
    • Excavation works at MIDC Station
    • Excavation works at MIDC Station
    • Excavation works at MIDC Station
    • Piling & Capping Beam works at MIDC Station
    • Piling & Capping Beam works at MIDC Station
    • Plung column works at Marol Naka Station
    • Piling works at Marol Naka Station
    • Piling work in progress at MIDC Station
    • Gantry rail fixing work in progress at MIDC Station
    • Excavation work in progress at MIDC Station
    76
    Package - 7
    09/12/2018
    • Base Slab and Rebar Progress at Vidhan Bhavan Station
    • Boom Placer Concreting at Cuffe Parade Station
    • Excavation Progress at Cuffe Parade Station
    • Excavation Progress in Grid 3-9 at Hutatma Chowk Station
    • Bird Eye view - Cuffe Parade Station
    • Bird Eye view - Churchgate Station
    • Excavation progress near Citibank at Hutatma Chowk Station
    • Permanent base slab progress at Vidhan Bhavan Station
    • Base Slab PCC at Cuffe Parade Station
    • Base Slab Casting at Vidhan Bhavan Station
    • Excavation in progress - Churchgate Station
    • Excavation in progress - Hutatma Chowk Station
    • Traffic deck erection in progress - Hutatma Chowk Station
    • Traffic deck erection in progress - Churchgate Station
    • Excavation Progress in Churchgate Station
    • Road diversion in VV Rao road in EE01 at Vidhan Bhavan Station
    • Strut Erection and Excavation Progress in Churchgate Station
    • TBM 2 Base slab Progress
    • Traffic Deck Erection Progress in Hutatma Chowk Station
    • Anchor drilling progress at Vidhan Bhavan Station
    • Excavation and beam erection progress at Churchgate Station
    • Excavation progress at Churchgate Station
    • Excavation progress at Hutatma Chowk Station
    • Excavation progress at Vidhan Bhavan Station
    • Excavation progress in NATM shaft at Cuffe Parade Station
    • Side view of NATM shaft at Cuffe Parade Station
    • Strut progress in Hutatma Chowk Station
    • Tunnel Progress from SCP to Vidhan Bhavan Station
    • Strut Erection Progress at Church Gate Station
    • Strut Erection Progress in Hutatma Chowk Station
    • Excavation Progress in SB at Cuffe Parade Station
    • Excavation Progress in NATM shaft at Cuffe Parade Station
    • Excavation Progress at Vidhan Bhavan Station
    • Excavation Progress at Hutatma Chowk Station
    • Excavation Progress at Church Gate Station
    • Anchor Drilling at Level -12.5 at Vidhan Bhavan Station
    • TBM Progress
    • Bird eye view
    • Excavation in progress at Vidhan Bhavan Station
    • Anchor drilling 12.5 level at Vidhan Bhavan Station
    • Anchoring Progress in Vidhan Bhavan Station
    • Excavation in progress
    • Excavation in progress at Cuffe Parade Station
    • Utility Support
    • Excavation in progress at Vidhan Bhavan Station
    • Side View of Cuffe Parade station NATM Shaft
    • Gantry erection in Churchgate Station
    • Strut Erection Progress at Hutatma Chowk Station
    • Traffic Deck Erection Progress at Churchgate Station
    • Segment Casting Yard Progress
    • Casting Yard Progress
    •  Excavation in Progress at Cuffe Parade Station
    • Excavation in Progress at Vidhan Bhavan Station
    53
    Package - 1
    09/12/2018
    • Casting Yard
    • Mumbai Central
    • Science Museum
    • Acharya Attre
    • Acharya Attre
    • Mahalaxmi
    • Casting Yard
    • Acharya Attre
    • Acharya Attre
    • Mumbai Central
    • Mumbai Central
    • Science Museum
    • Mahalaxmi
    • Worli
    • Science Museum
    • Acharya Attre
    • Mahalaxmi
    • Mahalaxmi
    • Mahalaxmi
    • Mumbai Central
    • Science Museum
    • Science Museum
    • Science Museum
    • Worli
    • Science Museum
    • Science Museum
    • Mumbai Central
    • Mumbai Central
    • Mahalaxmi
    • Mahalaxmi
    • Mahalaxmi
    • Acharya Attre
    • Acharya Attre
    • Acharya Attre
    • Acharya Attre
    • Aerial view - Mahalaxmi
    • Aerial view - Worli
    • Aerial view - Science Museum
    • Reinforcement fixing for traffic deck - Worli
    • Steel decking installation - Mumbai Central
    • 900 MM SWD diversion - Worli
    • Tanasa - 1 Initial Drive
    • Tunnel eye casting - Science Museum
    • Utility support installation - Acharya Attre
    • Excavation - Science Museum
    • Aerial view - Acharya Attre
    • MAHANAGAR Gas line diversion - Mahalaxmi
    • Temporary ring erection - TBM
    • Steel deck installation - Mumbai Central
    • Aerial view - Mumbai Central
    • Excavation - Science Museum
    • RCC Deck reinforcement fixing - Worli
    • Steel deck installation - Mahalaxmi
    • Steel deck installation - Mumbai Central
    • Secant Piling - Mahalaxmi
    • Secant Piling - Acharya Attre
    • Secant Piling - Worli
    • Excavation - Science Museum
    • Aerial view - Science Museum
    • Aerial view - Acharya Attre
    • Aerial view - Worli
    • Excavation - Science Museum
    • Excavation - Science Museum
    • Excavation - Science Museum
    • Tansa - 1 - Science Museum
    • RCC Deck construction - Acharya Attre
    • Steel Decking - Mahalaxmi
    • Steel Deck Construction - Mahalaxmi
    • Steel Deck Construction - Mumbai Central
    • RCC Deck construction - Worli
    70
    Package - 3
    25/11/2018
    • 1800 mm Dia. water line Diversion at CSIA Domestic Station
    • 900 mm Storm water drain at CSIA Domestic Station
    • Casting Yard
    • Gantry
    • Excavation at Domestic Airport Station
    • Excavation at Retrieval Shaft Sahar Road Station
    • Excavation at Retrieval Shaft at Domestic Airport Station
    • Excavation below Utility Support System at Sahar Road Station
    • Earthmat Grid (15-18) at Sahar Road Station
    • Excavation at International Airport Station
    • Initial Drive Finished Tunnel SC2-SSR Downline at International Airport Station
    • Excavation at Retrieval Shaft Sahar Road Station
    • Tunnel-Ring Installation at International Airport Station
    • Excavation at International Airport Station
    • Excavation at Domestic Airport Station
    • Excavation at Domestic Airport Station
    • Excavation below Utility Support System at Sahar Road Station
    • Excavation at Sahar Road Station
    • Suspender Erection at Utility Support System at Sahar Road Station
    • Excavation at International Airport Station
    • Base Slab Grid 11-13 at International Airport Station
    • Tunnel-Ring Installation at International Airport Station
    • TBM Retrieval Programme at International Airport Station
    • TBM Retrieval at International Airport Station
    • Tunnel ring installation at International Airport Station
    • Base Slab grid 10-13 work in progress at International Airport Station
    • Base Slab grid 18-20 at Sahar Road Station
    • Walkway at Sahar Road Station
    • Secant pile work in progress for NATM at Domestic Airport station
    • Excavation at Domestic Airport station
    • Excavation at Domestic Airport station
    • Excavation at International Airport Station
    • MMRCL MD visit at Package - 6 site
    • Inaugration of initial drive at International Airport Station
    • Initial drive started between International Airport Station to Sahar Road Station
    • Shadow road inauguration at Sahar Road Station
    • Shadow road commisioned on 27.07.18
    • Capping Beam at CSIA Domestic Station Box
    • TBM Parts at CSIA International station
    • Domestic NATM Secant pile
    • Domestic North retreival shaft excavation
    • Sahar station box excavation work
    • International retrieval shaft exacavation work
    • Sahar Utility hanging work
    • CSIA International station Excavation work
    • Subway work at Sahar road station
    • CSIA International shaft Launching shaft work
    • Excavation near Launching shaft
    • Excavation at International retrieval shaft
    • Launching shaft base slab at Launching shaft
    • Excavation at Sahar Retrieval shaft
    • Water Sprinkling for dus suppression at CSIA Domestic Station
    • Excavation at CSIA Domestic Station
    • Retrieval shaft excavation at Sahar Road Station
    • Subway construction at Sahar Road Station
    • Launching shaft excavation at Sahar Road Station
    • Launching shaft excavation at Sahar Road Station
    • Launching shaft excavation at Sahar Road Station
    • Launching shaft excavation at Sahar Road Station
    • Excavation at CSIA Domestic Airport Station.
    • Excavation at CSIA Domestic Airport Station.
    • 1800mm water line diversion at CSIA Domestic Airport Station
    • Excavation at CSIA International Airport Station.
    • Excavation at CSIA International Airport Station.
    • Rerrieval shaft excavation at CSIA International Airport Station.
    • Launching shaft excavation at CSIA International Airport Station.
    • Retrieval Shaft excavation at CSIA  International Station
    • Retrieval Shaft excavation at CSIA  International Station
    • Excavation at CSIA Domestic Station
    • Waler beam fixing at CSIA Domestic Station
    • Excavation at CSIA Domestic Station
    • Areal view of CSIA Domestic Station
    • Piling,Excavation & utility support  work at Sahar Road Station
    • Excavation at Sahar Road Station
    • Excavation at Sahar Road Station
    • Subway Sahar Road Station
    • Subway construction at Sahar Road Station
    • Subway at Shahar Road Station
    • Shadow road construction at Sahar road Station
    • Aerial view of CSIA International Station
    • Sahar shadow road construction
    • Retrieval Shaft at CSIA International Station
    82
    Package - 6
    25/11/2018
    • Siddhivinayak
    • Siddhivinayak
    • Casting Yard
    • Dadar
    • Nayanagar
    • Shitladevi
    • Dadar
    • Traffic Diversion
    • TBM - 2
    • Dadar
    • Shitladevi
    • Siddhivinayak
    • Dadar secant piling
    • Dadar toolbox
    • Nayanagar TBM - 1
    • Nayanagar TBM - 2
    • Shitladevi box overview
    • Nayanagar Shaft
    • Siddhivinayak Excavation
    • Cage preparation - Sitladevi
    • King post pile - Dadar
    • Siddhivinayak shaft excavation works
    • TBM Nayanagar
    • TBM Nayanagar
    • Aerial view of Nayanagar Site
    • Dadar
    • Dadar Construction Site
    • Aerial view of Siddhivinayak construction site.
    • Aerial view of Siddhivinayak construction site.
    • Segment Casting
    • Casting Yard
    • Shitladevi
    • Shitladevi
    • Siddhivinayak  piling
    • Siddhivinayak  piling
    • Casting Yard
    • Casting Yard
    • Nayanagar Shaft
    • Casting Yard
    • Dadarf road Diversion
    • Shitladevi road diversion
    • Nayanagar Shaft
    • Casting Yard Segments
    • Traffic Diversion Dadar
    • Guide wall casting at Dadar
    • Nayanagar Shaft Excavation
    • Nayanagar Shaft Excavation
    • Segment stacking
    • Traffic Diversion Dadar
    • Utility Diversion Dadar
    • Ring assembly testing
    • Nayanagar Excavation
    • Nayanagar Excavation
    • Nayanagar Excavation
    • Casting Yard segment casting
    • Casting Yard stacking bay
    • Bus queue shelter shifting
    • Shitladevi transplantation
    • Aarey transplantation
    • Nayanagar
    • Siddhivinayak
    • Siddhivinayak
    • Dadar traffic diversion
    • Dadar tree cutting
    • Dadar Utility Diversion
    • Shitladevi road works
    • Casting Yard - Segment casting
    • Dadar road works
    • Dadar & Shitladevi road works
    • Nayanagar micro pile gantry foundation
    • Nayanagar shaft excavation
    • Nayanagar shaft excavation
    • Capping beam Nayanagar
    • Casting Yard moulds
    • Casting Yard
    • Dadar house keeping
    • Nayanagar Micropile
    • Dadar road widening
    • Ravindra Natya Mandir
    • Casting Yard Gantry Foundation
    • Casting Yard segment
    • Dadar road
    • Siddhivinayak piling
    • Siddhivinayak piling
    • Dadar road widening
    • Casting Yard cage preparation
    • Shitladevi Road Excavation
    • Siddhivinayak
    • Siddhivinayak cage building
    • Shitladevi Road Widening
    • Siddhivinayak piling
    • Capping Beam at Nayanagar
    • Road Wideniing works at Dadar
    • Road Widening works at Dadar & Shitladevi
    • Segment Casting Yard
    • Segment Yard
    • Casting Yard
    • Nayanagar
    • Siddhivinayak
    • Sapling Distribution - Project Neighbourhood
    • Tree distribution in Project Neighbourhood
    • Tree Neighbourhood program
    • Project Neighbourhood
    • Tree Plantation
    104
    Package - 4
    25/11/2018
    • 1m Dia. Twin pipe for storm water drain diversion at Santacruz Metro Station
    • 1800 mm Dia. water line diversion at CSIA Domestic Station
    • 900 mm Storm water drain at CSIA Domestic Station
    • Suspender Erection at Utility Support System at Sahar Road Station
    • Tata Oil filled cable supporting in On Road portion at Vidhan Bhavan Station
    • Excavation progress in Grid 19-24 at Hutatma Chowk Station
    • Cable Tray Arrangement supported on Capping Beam for TATA Submarine Cable diversion at Dharavi Station
    • Hanging Arrangement across the Station for Diversion of TATA Submarine Cables at BKC Station
    • Multiple Water Pipelines of Dia (2.7m,-2.4m,-1.45m,-0.6m) Supported by Suspended Erection at Sahar Road Station
    • SEEPZ
    • Girgaon Station Phase - 05 Trenching for utility diversion
    • Support of xx mm Dia Water Pipe Line Beneath the station Box at Worli Station
    • Support of xx mm Dia Water Pipe Line Beneath the station Box at Worli Station
    • Truss Arrangement to House Multiple Mega Utilities at Sahar Road Station
    • UGC07 SEEPZ Station 900 mm Dia waterline supporting works.
    • Vidyanagari Station
    16
    Utility Shifting
    15/11/2018
    • MD. MMRC, Ms. Ashwini Bhide welcomes Hon'ble Chief Minister, Shri Devendra Fadnavis
    • Ms. Ashwini Bhide, MD MMRC said "MMRC hasn’t achieved the feat without its share of challenges but we could overcome them because of strong support from Hon'ble. Chief Minister, Shri Devendra Fadnavis ji, his effective war room and all other stakeholders!
    • Hon'ble. Chief Minister speaking on the occasion said, "The state government has embarked upon its journey to complete 270 km. Metro Network in MMR over next 3 to 4 years & Metro 3 is an important part of the same".
    • Hon'ble. Chief Minister, Shri Devendra Fadnavis witnesses the first TBM breakthrough of Mumbai Metro 3 at CSMIA-Terminal-2 station
    • Wainganga-1 commissioned on 8th, Jan 2018 bore at 1.26 km tunnel drilling its way for 259 days through rocky strata from Pali Ground, Marol to CSMIA T2 station
    • TBM Wainganga -1 breaks through the 1st tunnel at CSMIA-T2 station. An important milestone towards completing 33.5 km Metro-3 corridor
    • The Achievement: Team MMRC at the First Breakthrough.
    7
    First TBM Breakthrough of Mumbai Metro - 3
    24/09/2018
Top