Package - 2

Sr. No Nature of Work Status
1 Barricading

Barricading for CST Station Box, Wadala Casting Yard and WTC completed.

Barricading in Grant Road completed for Garden Side.

Barricading done for 331 RM out of 615 RM (Approx.)

2 Rehabilitation & Resettlement 

2nd round of Consultation meeting & negotiation with project affected residents / owners / tenants in progress for Kalbadevi and Girgaon station.

Compensation meeting in progress with project affected residents in Kalbadevi and Girgaon.

3 Traffic Diversion 

Permission for Traffic Diversion at Girgaon station received and road diversion started from 18th May 2017.

Trail run for traffic diversion at Grant road done on 20th July’2017 and road diversion started from 27th July’2017.

4 Geo-technical investigation

Geo-technical investigation for Stations as well as Tunnel completed. 

5 Tree Cutting/transplantation

CST - Total Progress - 41 , Scope - 80

CST - Transplantation - Total Progress - 44 , Scope - 90

Grant Road  - Total Progress - 26 , Scope - 26

Grant Road Transplantation - Total Progress - 21 , Scope - 21

Girgaon - Total Progress - 10 , Scope - 11

Girgaon Transplantation - Total Progress - 9 , Scope - 9

New Plantation at Aarey Colony  - Total Progress - 205 , Scope - 354

6 Building condition Survey

Pre - Condition Survey

Weekly Progress - 14

Total Progress - 557

Scope - 1085

Upload File: 
Date: 
Saturday, September 9, 2017 - 15:00
Package Type: 

Add new comment

Filtered HTML

  • Web page addresses and e-mail addresses turn into links automatically.
  • Allowed HTML tags: <a> <em> <strong> <cite> <blockquote> <code> <ul> <ol> <li> <dl> <dt> <dd>
  • Lines and paragraphs break automatically.

Plain text

  • No HTML tags allowed.
  • Web page addresses and e-mail addresses turn into links automatically.
  • Lines and paragraphs break automatically.
CAPTCHA

Please enter the letters displayed in the image below. If the image is not clear, click on "Can't read the text? Get a new image"

Image CAPTCHA
Top