Project Status

The MML-3 Project is divided into 18 main packages of ‘Project’ & ‘System’ wings.

Package wise status of the project is as under:

Packages Nature of Work Name of Contractor Amt Status Target for Contract Award
Package 1 Civil Works – Tunnels & Stations L&T-STEC JV Rs. 2,988.53 cr Letter of Acceptance Issued to Contractor Awarded
Package 2 Civil Works – Tunnels & Stations HCC-MMS JV Rs. 2,521.89 cr Letter of Acceptance Issued to Contractor Awarded
Package 3 Civil Works – Tunnels & Stations M/S DOGUS-SOMA Rs. 2,557.84 cr Letter of Acceptance Issued to Contractor Awarded
Package 4 Civil Works – Tunnels & Stations M/S CEC-ITD CEM-TPL JV Rs. 2,830.10 cr Letter of Acceptance Issued to Contractor Awarded
Package 5 Civil Works – Tunnels & Stations M/S J. Kumar-CRTG Rs. 2,817.02 cr Letter of Acceptance Issued to Contractor Awarded
Package 6 Civil Works – Tunnels & Stations M/S J.Kumar-CRTG Rs. 2,118.40 cr Letter of Acceptance Issued to Contractor Awarded
Package 7 Civil Works – Tunnels & Stations L&T-STEC JV Rs. 2,281.45 cr Letter of Acceptance Issued to Contractor Awarded
Package 8 Civil – Depot - - State Government's decision on Depot Site is Awaited -
Package 9 Plant & Equipment for Depot - - DPR Review/Design work for ‘PQ Preparation’ for System Bids started. May, 2017
Package 10 Track Works - - DPR Review/Design work for ‘PQ Preparation’ for System Bids started. May, 2016
Package 11 Traction - - IFB issued to bidder & Pre Bid meeting held on 10/02/2017 for package 11B & on 14/02/2017 for 11A Dec, 2016
Package 12 Signaling, Train control, PSD & Communications - - PQ Bid evaluation completed Feb, 2017
Package 13 Station Security System - - DPR Review/Design work for ‘PQ Preparation’ for System Bids started. May, 2017
Package 14 Automatic Fare Collection - - PQ Bid scheduled for opening on 3/02/2017 May, 2017
Package 15 Tunnel Ventilation & Environmental Condition System - - IFB issued to all Pre - Qualified bidders & Pre - Bid meeting scheduled on 28/02/2017 Jan, 2017
Package 16 Lifts & Escalators - - IFP for PQ issued in Newspaper on 3/02/2017. Pre - application meeting is scheduled on 22/02/2017 Jan, 2017
Package 17 Rolling Stock - - PQ under review (as per MoUD directives) Feb, 2017
Package 18 General Consultant - - General Consultants engaged. May, 2016
Top