Project Timeline

 

Concept of Metro, proposed for the first time in Mumbai

1969
 

Reflected in Development Plan

1991
 

Feasibility study carried out by MMPG

1997
 

Mumbai Metro Master Plan initiated by MMRDA

2003
 

Mumbai Master Plan prepared by DMRC

  • Length -146 km
  • Corridors –9
  • Phases –3 phases
2004
 

Public Consultation on Mumbai Metro Master Plan

2004
 

Metro Line –1 awarded on PPP

2006
 

Metro Line –2 awarded on PPP

2008
 

Line 3 preparatory works Initiated on PPP model; however, not found feasible on VGF model

2009
 

Project initiated for EPC model with JICA funding in 2011

2011

Prospective Timeline

 

2011 - 2013

  • Publication of revised DPR for fully underground Colaba-Bandra-SEEPZ Corridor
  • Alignment publication of MML - 3
  • Submission of Proposal to Government of India
  • Occurrence of Pre-PIB
  • Approval of JICA loan
  • Approval of PIB & Cabinet
  • Signing of Loan agreement
  • Public consultation for SIA & EIA
  • Approval of Government of India
  • Notification under Metro Act
  • Signing of loan agreement between GoI & JICA
 

2013 - 2015

  • Approval of State Cabinet
  • Approval of Maharashtra Govt.
  • PQ contractors for civil works-Tunnels & Stations
  • Appointment of General Consultants
  • Publishing of Tenders for civil works-Tunnels & Stations
 

2015 - 2017

  • Completion of Civil works (Tunnels & Stations)
  • Basic designs of System components
  • Issuance of Tenders for Systems/Rolling stock
  • Completion of Detailed design manufacturing & installation
 

2017 - 2020

  • Completion of P-way work
  • Completion of Testing & certification
  • Final Commissioning