Package - 1

Sr. No Nature of Work Status
1 Barricading

All encumbrance free area handed over have been barricaded

 

2 Rehabilitation & Resettlement 

Demolition works at Vidhan Bhavan taken up as and when front available

29/31 offices shifted

27/31 offices at Vidhan Bhavan demolished

Rehabilitation of eateries and few families within Vidhan Bhavan station boundary remaining

Alternate location for Police Chowky at Hutatma Chowk station remaining

3 Traffic Diversion 

In principle NOC for traffic diversion received from joint CP (Traffic) for the Project

Joint CP (Traffic) visited all station locations on 13th April 2017 to take stock of situation and has in principle agreed to the traffic diversion plans

Diversion effective at Hutatma Chowk from 18.05.17

North Bound Traffic at Captain Prakash Pethe Marg blocked for utility diversion since 05.07.17.

Diversion effective at Jamshedji Tata Road (Churchgate Station) from 19.07.17

4 Geo-technical investigation Geotechnical Investigations completed (61 boreholes)
5 Tree Cutting/transplantation

Works resumed on 19.05.17

282/354 Trees cut, 127/318 Trees Transplanted

390 new trees planted

6 Building condition Survey BCS works for 197/253 buildings completed.
Date: 
Sunday, July 23, 2017 - 17:45
Package Type: 

Add new comment

Filtered HTML

  • Web page addresses and e-mail addresses turn into links automatically.
  • Allowed HTML tags: <a> <em> <strong> <cite> <blockquote> <code> <ul> <ol> <li> <dl> <dt> <dd>
  • Lines and paragraphs break automatically.

Plain text

  • No HTML tags allowed.
  • Web page addresses and e-mail addresses turn into links automatically.
  • Lines and paragraphs break automatically.
CAPTCHA

Please enter the letters displayed in the image below. If the image is not clear, click on "Can't read the text? Get a new image"

Image CAPTCHA
Top