Package - 1

Sr. No Nature of Work Status
1 Barricading All encumbrance free area handed over have been barricaded
2 Rehabilitation & Resettlement

Vidhan Bhavan Station: Eatery Kutumbsakhi to be vacated from SVB

Hutatma Chowk Station: Alternate location for Police Chowky remaining

3 Traffic Diversion Phase-1 Traffic Diversions implemented at all station locations
4 Geo-technical investigation Geotechnical Investigations completed (61 boreholes)
5 Tree Cutting/transplantation

Cuffe Parade Station - 

Scope (To be transplanted/To be cut) - 110/165

Completed (Transplanted/Cut) - 96/155

Vidhan Bhavan Station - 

Scope (To be transplanted/To be cut) - 94/102

Completed (Tsransplanted/Cut) - 48/71

Church Gate Station - 

Scope (To be transplanted/To be cut) - 47/51

Completed (Transplanted/Cut) - 25/26

Hutatma Chowk Station - 

Scope (To be transplanted/To be cut) - 45/76

Completed (Transplanted/Cut) - 43/44 (Balance saved and need not be removed)

6 Building condition Survey BCS works for 245/251 buildings completed.
7 Tunneling Progress Not yet started.
8 Segment Production Progress  _________
9 Secant PilingProgress

Cuffe Parade Station -  Total completed -1371, Scope –1371(Only Station Box)

Vidhan Bhawan Station - Total completed -916, Scope – 1913

Church Gate Station - Total completed -639, Scope – 1,487

Hutatma Chowk Station - Total completed 1,000-, Scope – 1712

10 Excavation

Cuffe Parade Station :  56,830 cum. out of 2,75,531 cum. Completed

Vidhan Bhawan Station :   23,930 cum. out of 1,53,400 cum. Completed

11 Base Slab Progress    _________
Date: 
Sunday, April 15, 2018 - 12:00