Sr. No Nature of Work Status
1 Barricading Barrication works in MIDC, Marol Naka, SEEPZ, Casting yard & launching shaft is in progress.
2 Rehabilitation & Resettlement 

Hutment demolition in MIDC Area is in progress. Shops are removed in Marol Naka area.

3 Traffic Diversion  Traffic diversion at MIDC Road no. 7 completed.
Traffic diversion in Marol Naka station is in progress.
4 Geo-technical investigation  50 nos of borehole drilling & field tests completed.
5 Tree Cutting/transplantation

Tree Cutting

Marol Naka - 7 out of 9 completed

MIDC - 9 out of 11 completed

SEEPZ - 9 out of 12 completed

Tree Transplantation:

Marol Naka - 35 out of 50 completed

MIDC - 90 out of 130 completed

SEEPZ - 86 out of 115 completed

6 Building condition Survey  Building condition survey is in progress