Package - 2

Sr. No Nature of Work Status
1 Barricading

Barricading for CST Station Box, Wadala Casting Yard and WTC completed.

Barricading in Grant Road completed for Garden Side.

Structural Steel barricading for Median done at Grant Road.

Barricading in Girgaon completed for 619 RM out of 619 RM (Approx.)

2 Rehabilitation & Resettlement 

Rehabilitation & Resettlement is in progress.

Compensation meeting in progress with project affected residents in Kalbadevi and Girgaon.

3 Traffic Diversion 

Permission for Traffic Diversion at Girgaon station received and road diversion started from 18th May 2017.

Trail run for traffic diversion at Grant road done on 20th July’2017 and road diversion started from 27th July’2017.

Road diversion in Grant Road Phase-1 to start from 23rd Oct’2017

4 Geo-technical investigation

Geo-technical investigation for Stations as well as Tunnel completed. 

5 Tree Cutting/transplantation

CST - Total Progress - 42 , Scope - 80

CST - Transplantation - Total Progress - 52 , Scope - 90

Grant Road  - Total Progress - 28 , Scope - 28

Grant Road Transplantation - Total Progress - 21 , Scope - 21

Girgaon - Total Progress - 10 , Scope - 11

Girgaon Transplantation - Total Progress - 9 , Scope - 9

New Plantation at Aarey Colony  - Total Progress - 205 , Scope - 354

6 Building condition Survey

Pre - Condition Survey

Weekly Progress - 0

Total Progress - 779

Scope - 1085

7 Tunneling Progress

TBM - 1

Temporary ring: Total progress - 12, Scope - 12

CST - SKD: Total progress - 207, Scope - 478

TBM - 2

Temporary ring: Total progress - 12, Scope - 12

SCS - SKD: Total progress - 57

8 Segment Production Progress

Permanent Rings (including Upline & Downline)

SCS - SKD: Total progress - 960, Scope - 960

SKD - SGG: Total progress - 447, Scope - 680

SGG - SGR: Total progress - 292, Scope - 1828

SGR - SMC: Scope - 144

Temporary Rings (including Upline & Downline)

SCS: Total progress - 20, Scope - 20

SKD: Total progress - 17, Scope - 290

SGG: Scope - 418

SGR: Scope - 144

9 Secant Piling Progress

CST Station

Primary pile (LS): Total progress - 80, Scope - 80

Secondary pile (LS): Total progress - 78, Scope - 78

Primary pile (BS): Total progress - 279, Scope - 279

Secondary pile (BS): Total progress - 274, Scope - 274

Primary pile - Entry & Exit: Total progress - 221, Scope - 487

Secondary pile - Entry & Exit: Total progress - 203, Scope - 491

Grant Road Station

Primary pile: Total progress - 198, Scope - 366

Secondary pile: Total progress - 186, Scope - 428

Girgaon Station

Primary pile: Total progress - 81, Scope - 684

Secondary pile: Total progress - 61, Scope - 678

10 Excavation

CST Station

Launching shaft: Total progress - 25,317 Cum. Scope - 25,317 Cum.

Balance station: Total progress - 92,011 Cum. Scope - 1,21,983 Cum.

11 Base Slab Progress

_________

Upload File: 
Date: 
Friday, April 20, 2018 - 15:00