Land Requirement

Sr. No.   Permanent Land Required Temporary Land Required
Pvt Govt. / Semi Govt. Pvt Govt. / Semi Govt.
1 Station and allied facilities (MCGM, Home Dept, MHADA, PWD, etc.) 0.55 ha 8.70 ha 2.90 ha 12.00 ha
2 Traction Sub-Station (at 3 locations) - 0.60 ha - -
3 Construction Depot (12 pockets) 0.55 ha 8.70 ha 2.90 ha 12.00 ha
4 TBM worksites (12 pockets) - - - 7.00 ha
5 Casting yard (7 packages)* - - - 35.00* ha
6 Other allied & commercial uses - 3.72 ha - -
  Total 0.55 ha 13.02 ha 2.90 ha 62.20 ha

Total Land Required: 78.67 ha

Permanent: 13.57 ha

Temporary: 65.10 ha

Pvt: 3.45 ha

Govt: 75.22 ha

  • Private land acquisition is being done under sec126 of MRTP Act 1966 by negotiation to the extent possible.
  • MMRCL has set up Preliminary Hearing Committee to hear the suggestions and objectives.
  • Compensation Committee is also set up under the Chairmanship of former IAS officer Shri Sudhir Thakare.

Bird View

All images used are for illustrative purpose only.
Top